MSP Task Word Wrap?

B
Bob Duncan 👤 Member for 22 years 2 months
B
Bob Duncan 👤 Member for 22 years 2 months

Thank you.

I tried that but it forces a gap between the GANNT Chart bars which makes them look strange. They need to stay together to show the visual flow from one task to the next.



Can I overcome this problem somehow?



Bob.



ps. I’m using Project 2002.

W
Will Russell 👤 Member for 23 years 2 months

Bob,



Depending on which version of MSP you’re using you should be able to adjust individually the height of the task line this way the text will automatically wrap.