Unfortunately you cannot have it both ways!!
Thank you.
I tried that but it forces a gap between the GANNT Chart bars which makes them look strange. They need to stay together to show the visual flow from one task to the next.
Can I overcome this problem somehow?
Bob.
ps. Im using Project 2002.
Bob,
Depending on which version of MSP youre using you should be able to adjust individually the height of the task line this way the text will automatically wrap.
Will