yes yes yes, but does it support the mouse scroll wheel :P
Project code ID 4 -> 20 char fekking YES, that is good (and about 20 years behind time :P )
actually, Id have thought theyd do better than 64 char for Activity descriptions, but its enough I suppose...
if Im correct limits on ectivity code overall length have changed significantly, the limit is 64 in P3 but much longer (unlimited...?) in P3e as far as I heard. That may be a good or a bad thing, I sorta like the discipline of restricted code lengths. No more will I be able to shrug off requests for yet another user code with "sorry, we ran out after the 10th one you wanted, its a software constraint" *sigh*
"Is Primavera planning to discontinue support for P3?
Given the high demand, we are committed to support P3 through the end of 2010. During this support period, we will continue to implement patches to P3 as necessary, although we have no plans to enhance its functionality and no plans to certify P3 on new versions of Windows operating systems beyond XP.
Our goal is to do whatever is commercially reasonable to keep Primavera customers satisfied with and loyal to Primavera products. It is our hope that over the next year, existing P3 users will migrate to a future version of Primavera as we continue to add functionality."
This could be read to confirm with what you said about supporting "at least until 2010" it could also be read that "we wont support after 2010. Either way, around that date they will be dropping support and this is the info we have form their local offices here.
Not certifying it for Vista will choke it off either way.
Of course market demand may force a change in policy
Pv do still run P3 courses, at least they do in Holland / Belgium. Possibly only on demand though, Im not aware of a regular schedule, they have come here to teach P3 introductory courses in the last month
The funny thing here is, while we know that theyre going to drop maintenance support for P3 in 2010 / 2011 they (Pv) really dont seem to be trying to sell us P6. The cynical side of me says the Pv sales dudes think they will get more cash out of us by waiting till they drop support before upgrading. afaik, the "upgrade" afaik is free atm so I suppose theres no sales in it for the guys to get us to change over. Certainly at the moment they seem to be almost discouraging us from migrating, its kinda wierd.
A full answer to your question would be very long indeed. P5(6) is a stunning improvement on P3.
BUT IT IS NOT A UPGRADE.
It is a whole new world. Many P3 planners are "given" P5 and expected to just get on with the job, whereas it requires not just the individual planners to be extensively retrained, but the company to establish a project controls infrastructure and project controls proceedures that have not been required in the past.
How do you persuade your employers to migrate? The owners need to see a proper presentation of P5 as a BUSINESS system - not a planning system. Once they understand that P5 can help manage the business, not just print barcharts, you can get that decision.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
James,
If u want mouse scrolling with p3, then u need to do d following:
U need to use Microsoft-Intellipoint 4.1 mouse.
Log out of P3 --> Use the installation Disk that comes with the mouse, Install the driver --> Reboot your computer (open P3 & scroll)
Cheers,
Raviraj
yes yes yes, but does it support the mouse scroll wheel :P
Project code ID 4 -> 20 char fekking YES, that is good (and about 20 years behind time :P )
actually, Id have thought theyd do better than 64 char for Activity descriptions, but its enough I suppose...
if Im correct limits on ectivity code overall length have changed significantly, the limit is 64 in P3 but much longer (unlimited...?) in P3e as far as I heard. That may be a good or a bad thing, I sorta like the discipline of restricted code lengths. No more will I be able to shrug off requests for yet another user code with "sorry, we ran out after the 10th one you wanted, its a software constraint" *sigh*
Hi all.
Below are some difference according to Primavera.
Feature P3 P3e/c
Project Code ID Characters Input 4 20
Project Description Characters Input 48 64
Project Time Unit: switching between Days and Hours No Yes
Activities Character Input 10 20
Project Layout At project level At Project & Global levels
Project Layout with Filters no yes
Security Access for Project Managers Sharing Activites in Same Project Controlled by WBS no yes
Activites Codes At project level At Project & Global levels
Inter-Project Linking of 2 Independent Projects Very tedious, requires external application Very easily done within application
Resource Calender: switching between days and hours No Yes
Number of Baselines Comparision 1 only 3
Number of Baselines in Project 2 50
Number of Resource Costs 1 only Up to 5 costs can be defined
Stacked Histogram no yes
Batched Report no yes
Time-Scaled Logic diagram no yes
Portfolio Analysis no yes
Setting Constraints Primary only Primary & Secondary
Time-Scale 2 tier 3 tier
Coding Project Project/Global
Undo Feature no yes
Export/Import of Projects Very tedious, requires external application (MSP/Excel) Very easily done within application (MSP/Excel/P3)
Hi all,
I suggest that learn the fundamentals from P3 then explore P5. Its a different environment but if you know your basics it wont be much of a problem.
Regards,
Ed
From Pv website;
http://www.primavera.com/customer/products/p3migrate_faq.asp
"Is Primavera planning to discontinue support for P3?
Given the high demand, we are committed to support P3 through the end of 2010. During this support period, we will continue to implement patches to P3 as necessary, although we have no plans to enhance its functionality and no plans to certify P3 on new versions of Windows operating systems beyond XP.
Our goal is to do whatever is commercially reasonable to keep Primavera customers satisfied with and loyal to Primavera products. It is our hope that over the next year, existing P3 users will migrate to a future version of Primavera as we continue to add functionality."
This could be read to confirm with what you said about supporting "at least until 2010" it could also be read that "we wont support after 2010. Either way, around that date they will be dropping support and this is the info we have form their local offices here.
Not certifying it for Vista will choke it off either way.
Of course market demand may force a change in policy
Primavera has never said that they would drop support of P3 in 2010. Joel Koppelman, CEO of Primavera has publicly said:
1. We promise to sell and support P3 for as long as our customers want to purchase it.
2. We will support SureTrack and P3 for at least through the year 2010.
I heard both of these statements at various Primavera conferences.
Pv do still run P3 courses, at least they do in Holland / Belgium. Possibly only on demand though, Im not aware of a regular schedule, they have come here to teach P3 introductory courses in the last month
The funny thing here is, while we know that theyre going to drop maintenance support for P3 in 2010 / 2011 they (Pv) really dont seem to be trying to sell us P6. The cynical side of me says the Pv sales dudes think they will get more cash out of us by waiting till they drop support before upgrading. afaik, the "upgrade" afaik is free atm so I suppose theres no sales in it for the guys to get us to change over. Certainly at the moment they seem to be almost discouraging us from migrating, its kinda wierd.
I dont think Premavera run courses for P3 any more.
They are trying to drop P3, but the weight of users means they have extended support for the time being.
You may be able to locate an independant trainer for P3, though.
Craig,
A full answer to your question would be very long indeed. P5(6) is a stunning improvement on P3.
BUT IT IS NOT A UPGRADE.
It is a whole new world. Many P3 planners are "given" P5 and expected to just get on with the job, whereas it requires not just the individual planners to be extensively retrained, but the company to establish a project controls infrastructure and project controls proceedures that have not been required in the past.
How do you persuade your employers to migrate? The owners need to see a proper presentation of P5 as a BUSINESS system - not a planning system. Once they understand that P5 can help manage the business, not just print barcharts, you can get that decision.