job must finish by

L
Luca Basile 👤 Member for 22 years 11 months

More over Your Client accepted to have in the scedule activities with constrains (like must finish, must start, early start or finish, etc ...).



In my experience they accept only in the interface milestone to compare with another milestone at the end of the "work package".



If for example You put a must start on 10 april for a pole installation, it mean is missing all the logic for the procurement and delivery of it.

M
MK TSE 👤 Member for 24 years 3 months

I think it is the network architecture problem rather P3 problem. To indue a project must finish on, at least 2 level can be control and either one of them can perform: at project overview and/or to the last activity.



However, if both client and contractor are in different sub-projects and merge to a master project, there will be another story.

Forum Sponsor

Top Posters

MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts