clause14 and baseline program

A
ashraf alawady 👤 Member for 19 years 11 months

clause 14 in the general condition of contract is specifing the contractor responsibilties to submit a work program within 28 days from issuing the letter of acceptance from the client to the contractor.



clase 14 is divided into 4 sub clauses(14.1,14.2,14.3 and 14.4)

clause 14.1 is discripe the program of work to be submitted in the begeining of the project not later than 28 days after the date of letter of acceptance and after reviewing and approval of such program by the engineer/client this will be the apprved base line program.

clause 14.2 is discripe the coditions and requirements to submit revised program of work if at any time appear to the engineer that the actual progress of the works does not conform to the program to which consent has been given under sub-clause 14.1












Featured Partner

Top Posters

jeoffrey reyes
15 posts
Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts