I have just done a report to do exactly this. Quite easy to do using the report wizard. Just have a go, you can’t do any damage, you can always delete your new report and have another go. It gets easier each time you do it.

D
Dieter Wambach 👤 Member for 19 years 6 months

Hi Suresh



You are right. In that view you can find the project but not WBS. A workaround would be, to create an activity code "a_wbs" and assign it to the activities. Folowing this code you can filter.

This way I did it already in the past because in some of the reports you can’t filter or group according to WBS, but in most cases according to an activity code.

Regards

Dieter

S
Suresh Sankarankutty PMP 👤 Member for 19 years 11 months

Dieter,

Yes, Assignments is the best but still in the filter i dont find the WBS or I am not able to put the filter liem " Activtity Name contains = " xyz" . There is only Activity name = Equal or not equal .


D
Dieter Wambach 👤 Member for 19 years 6 months

Hi Suresh



A different way would be: you’ll change to the view "Assignment" and then group by activity.

If you want to create a report, select the group "Activity Resource&Role assignments.

Regards

Dieter

Featured Partner

Top Posters

Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts