Im sorry. You are right. It seems that in this new version 5.0 Start float and finish float are the same in Interruptible activity and constraint activity.
Ill check with some of my college and feedback you in case I find the answer.
Thanks for your consideration,by the way as I checked difference total float for activity that has suspend and resume dates and also for activity which has constraint,I couldnt find any difference(as you know P3e calculates based on remaining early dates)would you please clarify the issue.
Start and Finish float are usually the same, however they can be different in the following situations.
1. When using Suspend & Resume
2. When using constraints
3. Hammock/Level of Effort activities
4. WBS activities
5. Summary calculations that get their dates from detailed activity information
The easily seen situation is Level of effort activities. The first activity and last activity of LOE activity usually have different float. So the schedule option can bring into play now.
This is a topic more for the purists. For a normal activity until today I wasnt able to realize real difference. For WBS-Summary there are, but I dont know why. I didnt analyze float on WBS-summary activities, since it was not important for me. Others may know an answer.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Kian!
Im sorry. You are right. It seems that in this new version 5.0 Start float and finish float are the same in Interruptible activity and constraint activity.
Ill check with some of my college and feedback you in case I find the answer.
Thanks
Khuong
Dear Khuong
Thanks for your consideration,by the way as I checked difference total float for activity that has suspend and resume dates and also for activity which has constraint,I couldnt find any difference(as you know P3e calculates based on remaining early dates)would you please clarify the issue.
Regards
Kian,
Its actually very simple: If one single activity has both SS and FS relationships, the start float and finish float can be different.
H.T.H.
Hi Kian
Start and Finish float are usually the same, however they can be different in the following situations.
1. When using Suspend & Resume
2. When using constraints
3. Hammock/Level of Effort activities
4. WBS activities
5. Summary calculations that get their dates from detailed activity information
The easily seen situation is Level of effort activities. The first activity and last activity of LOE activity usually have different float. So the schedule option can bring into play now.
Thanks
Khuong
Kian
This is a topic more for the purists. For a normal activity until today I wasnt able to realize real difference. For WBS-Summary there are, but I dont know why. I didnt analyze float on WBS-summary activities, since it was not important for me. Others may know an answer.
Regards
Dieter