Testing - calendar days
Forum Sponsor
Top Posters
Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Hi Dina,
You said: concerning the snag it should be 7 days calender
In my opinion snag can be done either 6 or 7 days, it is management option.
can you explain why 7 cal
Rahmat,
On air freight, not good for a plane to take rest in the mid air, LOL.
DO you have a serious answer even one
Cheers,
In addition, dont use 5 or 6 days for shipment neither air freight. Not good to take a rest in the ocean or airport.
Sincerely yours.
Hi too,
5 days for Engineering, 6 days for Construction. We need rest at least 1 day in a week. Curing time no need rest because its natural action. Use 7 days when u r project is delay but u will spend more money to pay the acceleration costs.
Cheers
For testing, it should be 7 days calender, but for governmental inspection it should be 5 days calender depending on holidays.
concerning the snag it should be 7 days calender