Are you suggesting that the use of deadlines gives different results each time you use them? I have found the impact of a deadline on task slack to be quite predictable.
Just a word of advice. Critical path calculations, using the software, are notoriously unreliable. If you have used any date constraints or "Deadline" dates etc, all these will be calculated as part of the critical path. If your schedule is fully networked and linked, and allowed to "float" with no "deadlines", then you have a reasonble chance of getting a reliable result.
You can insert the field called "Critical" into the gantt chart. If it is Yes then the task is critical. You can also look at the Detail Gantt view to see the Critical Tasks as Red bars on the Gantt chart.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Are you suggesting that the use of deadlines gives different results each time you use them? I have found the impact of a deadline on task slack to be quite predictable.
Ahmed,
Just a word of advice. Critical path calculations, using the software, are notoriously unreliable. If you have used any date constraints or "Deadline" dates etc, all these will be calculated as part of the critical path. If your schedule is fully networked and linked, and allowed to "float" with no "deadlines", then you have a reasonble chance of getting a reliable result.
HTH.
James.
You can insert the field called "Critical" into the gantt chart. If it is Yes then the task is critical. You can also look at the Detail Gantt view to see the Critical Tasks as Red bars on the Gantt chart.