EPS Activity code values in P5

R
Rodel Marasigan 👤 Member for 19 years 7 months

Patricia,



No impact at all as P3e/P5 assigned max 3 baseline at a time. Actually its four (4) if you include Project Baseline for EV calculation plus Primary, Secondary and Tertiary baseline. It’s just creating another record into PMDB Database same as creating a project.



Regards,

Rodel

P
Patricia Le Clainche 👤 Member for 19 years 1 month



Rodel,



I was convinced we were limited to a maximum of 50 baselines for a project. So thanks for this info.



Nevertheless, if we are not limited in Baseline creation, could it have an impact on performance of P5 ; in this case, it would be better having a limit.



Regards.

Patricia


R
Rodel Marasigan 👤 Member for 19 years 7 months

James,



Yes there are limits depends on your setting on Admin Preferences. To set the limit select Admin-> Admin Preferences then select Data Limits tab.



EPS/WBS tree - 1 to 50

OBS tree - 1 to 25

Resources tree - 1 to 25

Role tree – 1 to 25

Cost Account tree – 1 to 25

Activity Code tree – 1 to 25

Resources Code tree – 1 to 25

Project Code tree – 1 to 25

Maximum Activity Code per project – 0 to 500

Maximum Baseline per project - no limit or up to valid integer value



You can also set the ID code length



Regards,

Rodel

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts