What I am trying to do and seem unable to though is to change resource type from Labour to Non-labour.
I firstly thought I could just change the type on the resource screen but it says I cant do that as they are allocated to the tasks.
So I copied the resources which need changing and on the new version changed the type as required. I then tried to carry out a global change to change them. Unfortunately it will not allow me within global change assign a non-labour resource!
Any ideas how I can get round this?
The problem I have is I am importing P3 files via Suretrak and in Suretrak there are no options to change resource type.
If you mean you want to assign resource B instead of resource A, it can easily be done by global change. If you want to change the type of resource A from say labour to material, you dont need global change. Change it in resource directory and it will be reflected globally.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Oliver,
That is what I am trying to do however after setting up the Non-Labour resource it will not allow me to select it in the Global Change command
I have not got an budget/actual figures related to the resources so I thought it would be quite easy but for some reason it doesnt like it!!
Matt
Matt,
Having looked closer at global change it appears you can only filter by resource type and you cant make a change between labour/nonlabour.
How about creating a new resource with the same name, tarif and calendar but as a non-labour resource. Then doing a global change to swap them over?
It may leave you having to input the budgeted/actual units though, not sure?
Oliver
Oliver,
Thanks for the help!
What I am trying to do and seem unable to though is to change resource type from Labour to Non-labour.
I firstly thought I could just change the type on the resource screen but it says I cant do that as they are allocated to the tasks.
So I copied the resources which need changing and on the new version changed the type as required. I then tried to carry out a global change to change them. Unfortunately it will not allow me within global change assign a non-labour resource!
Any ideas how I can get round this?
The problem I have is I am importing P3 files via Suretrak and in Suretrak there are no options to change resource type.
Thanks,
Matt
Matt,
Go on Global Change.
New.
(Select subject area) Activity Resource Assignments.
The rest is self explanatory.
A parameter of resource type will allow a change between labour, material etc.
A parameter for Resource NameID will allow a global change of resource. (Person specific)
Oliver
If you mean you want to assign resource B instead of resource A, it can easily be done by global change. If you want to change the type of resource A from say labour to material, you dont need global change. Change it in resource directory and it will be reflected globally.