That is great !!!
Keep on planning.....
Regards
That really helps. This forum is great!
Thanks for your time, David and Oliver!
I agree with David,
you must have relationships between your activities in order to schedule the work. Otherwise all activities will move to the data date as there is nothing telling them they cant start immediately.
Hi There,
You are importing activities.Ok.
But if there is no relationship b/w activities, whether you import it or not, it is logical to see the start dates as data dates on the program.
Start dates, durations and finish dates are not enough to create a cpm. Relationship of those activites has to be defined as well.
Hope this helps
I am not importing relationships, just activities.
Can you create WBS by importing?
Hi There,
Did you check the relationship of activities?
I mean, while importing or exporting are you also importing or exporting predecessors or successors of activities.
It may cause such problem.