Minhas, Im sorry, I noticed that you said "not in footer", but not that you also said "not in . . . bar chart area".
I dont think there is any way to add them at the bottom of the columns. It can of course be a column, but that would use up a column for all displayed activities.
Thank you for quick reply. I appreciate your quick reply.
The way you mentioned I went through and solved my problem. Again , still I am getting those notes in bar chart area not in at the bottom of activity column area.
I dont think we can attach any notes at that area in p3e.
One more thing, I couldnt found edit current bar .I used to edit current bar in suretrack, ms project but how can we edit in p3e. in p3e if we select the current bar it opens and edit all bars not a single bar.
Make sure that this Notebook Topic is ticked in the Admin Category/Notebook Topics menu as being only for Activity. (Thats not all that important, but it will mean that it wont come up for selection if you add Notebook Topics at other levels.) Also that topic should only be added to the last activity, using the Notebook tab for that activitys detail. Youve probably done both those things already, or at least the second one.
Then go to the Bar dialog (View/Bar, or use the icon, or right-mouse click in the bar area), select the "current" bar and the Bar Labels tab, and add that Notebook Topic in the position you want it, most likely "right". It should then appear with the activity it has been assigned to, and you can size and shape it so that all of it is visible.
Or, add a Notebook Topic or UDF to the finish activity only, and then attsch it to the current bar. A Notebook Topic is potentially more sophisticated, because its a RTF field.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi musawar,
I have never worked in P3e, but yaa definitely its possible to do it in P3. Options in P3 and P3e are different in this case.
In P3 it shows,
Activity Detail
Edit activity
DElete activity
Dissolve activity
Extract Activity
Bars
Format Selected Bars.
Dear Raviraj,
Thanks for your reply.
In P3e I couldnt found "Formate Selected Bar" . On right clich on bar it shows following options and I checked all options :
Actvities details
Bar...,
Bar chart options...,
time scale...
attachment....
Thanks,
Musawar
Dear Arthur,
Thanks for your reply. I wrote all my comments on bar chart area.
Further, please dont say sorry.
Takecare
Minhas
Minhas, Im sorry, I noticed that you said "not in footer", but not that you also said "not in . . . bar chart area".
I dont think there is any way to add them at the bottom of the columns. It can of course be a column, but that would use up a column for all displayed activities.
Dear Minhas,
To edit the current bar, right click on the bar and select "Format Selected Bar" and then "Modify Bar format".
This should solve your purpose.
Thanks,
Raviraj
Dear Arthur,
Thank you for quick reply. I appreciate your quick reply.
The way you mentioned I went through and solved my problem. Again , still I am getting those notes in bar chart area not in at the bottom of activity column area.
I dont think we can attach any notes at that area in p3e.
One more thing, I couldnt found edit current bar .I used to edit current bar in suretrack, ms project but how can we edit in p3e. in p3e if we select the current bar it opens and edit all bars not a single bar.
If you know please let me know.
Regards,
Minhas
Make sure that this Notebook Topic is ticked in the Admin Category/Notebook Topics menu as being only for Activity. (Thats not all that important, but it will mean that it wont come up for selection if you add Notebook Topics at other levels.) Also that topic should only be added to the last activity, using the Notebook tab for that activitys detail. Youve probably done both those things already, or at least the second one.
Then go to the Bar dialog (View/Bar, or use the icon, or right-mouse click in the bar area), select the "current" bar and the Bar Labels tab, and add that Notebook Topic in the position you want it, most likely "right". It should then appear with the activity it has been assigned to, and you can size and shape it so that all of it is visible.
Dear Arthur,
Thank you for helping me.Thanks for helping me. I have added notebook topic but how can I attach that text with current bar.
Can you please write attachment procedure.
Thanks
Minhas
Or, add a Notebook Topic or UDF to the finish activity only, and then attsch it to the current bar. A Notebook Topic is potentially more sophisticated, because its a RTF field.
Add a text attachment to that activity? In the bar-chart area, right-mouse click on the activity; Attachments/Text.