change of WBS when Importing P3 to P6
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Chris
View Activities: You have the columns
- WBS; shows the complete hierarchy
- WBS Name; Shows the name of that WBS-node
- WBS Path; Shows the code without the upper nodes
For you WBS Name or -Code I assume then it will be shown with each activity.
Summary lines: Group & Sort: Group By WBS, unmark: Show ID Code
Regards
Dieter
Thanks Dieter!
May I know how to hide the WBS Code? or just say Show only WBS name.
Because what the problem is upon I imported the program with the project ID CP00 to P6 The WBS was turned to CP00.BCA instead of BCA only
Chris
This is by design. The first level of the WBS is the project itself. If Youll show the WBS, the complete path will be shown. Alternative: Just show WBS-Name.
Regards
Dieter