change of WBS when Importing P3 to P6

J
James bid 👤 Member for 16 years 8 months
D
Dieter Wambach 👤 Member for 19 years 5 months

Chris



View Activities: You have the columns

- WBS; shows the complete hierarchy

- WBS Name; Shows the name of that WBS-node

- WBS Path; Shows the code without the upper nodes

For you WBS Name or -Code I assume then it will be shown with each activity.



Summary lines: Group & Sort: Group By WBS, unmark: Show ID Code



Regards

Dieter

J
James bid 👤 Member for 16 years 8 months

Thanks Dieter!



May I know how to hide the WBS Code? or just say Show only WBS name.



Because what the problem is upon I imported the program with the project ID CP00 to P6 The WBS was turned to CP00.BCA instead of BCA only

D
Dieter Wambach 👤 Member for 19 years 5 months

Chris



This is by design. The first level of the WBS is the project itself. If You’ll show the WBS, the complete path will be shown. Alternative: Just show WBS-Name.



Regards

Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts