Thanks to everyone who posted a reply on this thread!
I really like this site and everyone seems not only helpful but knowledgable, too.
I found my answer using the National Electical Contractors Associations "The Effect of Temperature on Productivity" published in 1974 to extrapulate the intel that I needed.
The effects of extreme combinations of temperature and humidity on electrical labor productivity are identified. The results are presented in a series of tables and charts, which provide a powerful tool that can be used by contractors to adjust their bids during the bidding process and to support requests for time extensions and compensation during the construction process. To purchase this study along with the other six studies that comprise this entire report, see Index No. 5079CK - Productivity: Quantifying the Impacts of Adverse Working Conditions on Electrical Construction (Productivity Studies Kit).
View Related files (Note: these are in PDF format)
in some areas, it goes up to 53 degrees celcius, from around 8:00 am to 4:00 pm, people cannot work continuously for an hour if the work is outdoor, if its indoor, youll need air, at least provide them with a fan.
It is evident that extreme heat impacts on the productivity of your labour. My opinion: depending on your planning unit, you can adjust your calendar to capture this impact. Consider this scenario:
Temperature: 110 degrees Fahrenheit
Activity: laying of bricks
Budgeted quantity BQ: 100 hours
Number of men: 2 per shift
Shift: 2 shifts @ 12 hours per shift
Assuming that the BQ is not under estimated or over estimated, if the work force is 100% productive, then the original duration should be 50 hours. For argument sake, I want to assume that the productivity of the work force under extreme heat is 60%. You can adjust your calendar for the period (months) of the shut down to compensate the effect of the heat by selecting non work hours approximately 5 hours per shift. Your original duration is still 50 hrs, but your calendar will have 7 productive hrs to do the job per shift. This makes your bars longer. I hope this makes sense.
I can’t help you too much here I’m afraid, but you might get a bit of useful information from this thread on the forum. If you need more detail, click on the envelope icon next to any of the names, you’ll then be able to send a private message to that person and can ask them for more detail.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks to everyone who posted a reply on this thread!
I really like this site and everyone seems not only helpful but knowledgable, too.
I found my answer using the National Electical Contractors Associations "The Effect of Temperature on Productivity" published in 1974 to extrapulate the intel that I needed.
If anyone is looking for more info, look here:
http://www.necanet.org/store/index.cfm?fuseaction=search_results_sites&…
The Effect of Temperature on Productivity
Published: 2004
Description:
The effects of extreme combinations of temperature and humidity on electrical labor productivity are identified. The results are presented in a series of tables and charts, which provide a powerful tool that can be used by contractors to adjust their bids during the bidding process and to support requests for time extensions and compensation during the construction process. To purchase this study along with the other six studies that comprise this entire report, see Index No. 5079CK - Productivity: Quantifying the Impacts of Adverse Working Conditions on Electrical Construction (Productivity Studies Kit).
View Related files (Note: these are in PDF format)
Table of Contents
Index Number:
5072-04 Format:
Thanks again!
Very Respectfully,
in some areas, it goes up to 53 degrees celcius, from around 8:00 am to 4:00 pm, people cannot work continuously for an hour if the work is outdoor, if its indoor, youll need air, at least provide them with a fan.
but in my case, oh its very cold in here...
William,
It is evident that extreme heat impacts on the productivity of your labour. My opinion: depending on your planning unit, you can adjust your calendar to capture this impact. Consider this scenario:
Temperature: 110 degrees Fahrenheit
Activity: laying of bricks
Budgeted quantity BQ: 100 hours
Number of men: 2 per shift
Shift: 2 shifts @ 12 hours per shift
Assuming that the BQ is not under estimated or over estimated, if the work force is 100% productive, then the original duration should be 50 hours. For argument sake, I want to assume that the productivity of the work force under extreme heat is 60%. You can adjust your calendar for the period (months) of the shut down to compensate the effect of the heat by selecting non work hours approximately 5 hours per shift. Your original duration is still 50 hrs, but your calendar will have 7 productive hrs to do the job per shift. This makes your bars longer. I hope this makes sense.
Cheers
Ifeanyi
Hi William,
I can’t help you too much here I’m afraid, but you might get a bit of useful information from this thread on the forum. If you need more detail, click on the envelope icon next to any of the names, you’ll then be able to send a private message to that person and can ask them for more detail.
Chris Oggham