A Prime Cost (PCs) is an agreed, reasonable estimate for materials (fixtures and fittings) which you may not have selected at the time of entering into the contract. Usually, PCs are one-off items, however they can relate to a large number of items when the labour cost remains constant. Examples may include kitchen and bathroom items.
A Provisional Sum (PSs) is a reasonable estimate for material and labour of a particular part of the home which the builder cannot give a definite price for. The reason being the owner had not decided what the want at the time of entering into the contract. Examples are pool and landscaping.
A Prime Cost or P.C. sum is an item in the BoQ used to define some form of special work for a service or article to be incorporated into the Works. It should have a secondary item for the tenderers to fill in for their work in taking delivery, offloading, fixing possibly, and overheads and profit as a percentage or a fixed sum.
A Provisional Sum is the a sum to be expended ONLY on the instructions of the Engineer for some task which was not defined at tender stage. Valuation will be done at applicable contract rates or new rates as in the Variation clause.
Definitions of Provisional Sums are in Sub-Clause 1 of FIDIC 99 and how to deal with them in S-C 13.5
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
A Prime Cost (PCs) is an agreed, reasonable estimate for materials (fixtures and fittings) which you may not have selected at the time of entering into the contract. Usually, PCs are one-off items, however they can relate to a large number of items when the labour cost remains constant. Examples may include kitchen and bathroom items.
A Provisional Sum (PSs) is a reasonable estimate for material and labour of a particular part of the home which the builder cannot give a definite price for. The reason being the owner had not decided what the want at the time of entering into the contract. Examples are pool and landscaping.
Regards.
A Prime Cost or P.C. sum is an item in the BoQ used to define some form of special work for a service or article to be incorporated into the Works. It should have a secondary item for the tenderers to fill in for their work in taking delivery, offloading, fixing possibly, and overheads and profit as a percentage or a fixed sum.
A Provisional Sum is the a sum to be expended ONLY on the instructions of the Engineer for some task which was not defined at tender stage. Valuation will be done at applicable contract rates or new rates as in the Variation clause.
Definitions of Provisional Sums are in Sub-Clause 1 of FIDIC 99 and how to deal with them in S-C 13.5