Question

R
ram prasad 👤 Member for 19 years 3 months
M
Marcio Sampaio 👤 Member for 20 years 8 months

A Prime Cost (PC’s) is an agreed, reasonable estimate for materials (fixtures and fittings) which you may not have selected at the time of entering into the contract. Usually, PC’s are one-off items, however they can relate to a large number of items when the labour cost remains constant. Examples may include kitchen and bathroom items.



A Provisional Sum (PS’s) is a reasonable estimate for material and labour of a particular part of the home which the builder cannot give a definite price for. The reason being the owner had not decided what the want at the time of entering into the contract. Examples are pool and landscaping.



Regards.

B
Bryan Russell 👤 Member for 20 years 7 months

A Prime Cost or P.C. sum is an item in the BoQ used to define some form of special work for a service or article to be incorporated into the Works. It should have a secondary item for the tenderers to fill in for their work in taking delivery, offloading, fixing possibly, and overheads and profit as a percentage or a fixed sum.



A Provisional Sum is the a sum to be expended ONLY on the instructions of the Engineer for some task which was not defined at tender stage. Valuation will be done at applicable contract rates or new rates as in the Variation clause.



Definitions of Provisional Sums are in Sub-Clause 1 of FIDIC 99 and how to deal with them in S-C 13.5

Featured Partner

Top Posters

MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts