Engineering Schedule

M
Mehdi Rashidi Alangeh 👤 Member for 22 years 11 months

Dear Choudhary,

I think this question based on project. according to this issue you must define stages from engineering Dep, Such as:

1- Conceptual Design

2- Basic Design

3- Detail Design

4- ....



and for ang stage defing items breakdown , such No document , No manporer , etc and definf stage for issue, suche as IFC( Isuue for comment:20%-30%), IFA ( Issue for approved : 30%-50%) , APD ( approved 10%), AFC ( Approved for construction :10%)



Regards


Z
Zq qz 👤 Member for 23 years

then determine progress by MANHOURS

30% DESIGN stage - 25 % <==PERCENT FACTOR

60 % design stage - 25 % <==PERCENT FACTOR

90 % design stage - 30 % <==PERCENT FACTOR

100% design stages - 20 % <==PERCENT FACTOR



EXAMPLE DWG A: BUDGET MANHOUR = 200

EARNED MANHOUR= BUDGET MANHOUR X PERCENT FACTOR X PROGRESS



30% DESIGN stage - 200 X 25 % X 100 = 50 MANHOURS

60 % design stage - 200 X 25 % X 50 = 25 MANHOURS

90 % design stage - 30 %

100% design stages - 20 %

===============================================

EARNED ============================75 MANHOURS

% PROGRESS = 75 / 200 = ???????



tHEN FOR A GROUP OF DWGS YOU CAN DETERMINE PROGRESS AT DIFFERENT STAGES. BY LOCATION , AREA ETC.............

N
Nishikant Choudhary 👤 Member for 23 years 7 months

i appreciate the progress norms that is being advised . I would like to know as to how i should proceed with the manhours calculation as the unit of progress measurement.





Thx

Z
Zq qz 👤 Member for 23 years

gUYS,

I think you can do also this method:

Make a group i.e By Decipline

then determine progress by work matrix or work step i.e by:

30 % design stage - 25 %

60 % design stage - 25 %

90 % design stage - 30 %

100% design stages - 20 %



maybe with this method you have only less than 50 activities.

T
Tara Muddappa 👤 Member for 23 years 5 months

Hi Nishant,



Since the duration of the project you monitor is just 7 months,you are better of grouping these documents as one package.



Each package make a fragnet to truely represent logic and manpower resource and later on retrieve your fragnets to the

main network or program.



Regards,



Tara Muddappa

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts