Open the folder where you saved the file. Look for a file that ends with "LOG" (i.e if your file name is "SMKD" the file will be "SMKDLOG"). Delete this file and reopen your project.
The log records will no longer be present. You may decide to add additional log or simply close your project. A new "LOG" file will be created automatically in the folder where the previous "LOG" file was located.
Alternatively, a colleague just advised me that after exporting to a dbf file - insert a new column called Delete - then populate with the letter L - finally, import the data.
You can try through export/import tools. You can first export to a dbf file your logs, then open in excel and emptying them and finally import again. The result will be no log at your schedule.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Open the folder where you saved the file. Look for a file that ends with "LOG" (i.e if your file name is "SMKD" the file will be "SMKDLOG"). Delete this file and reopen your project.
The log records will no longer be present. You may decide to add additional log or simply close your project. A new "LOG" file will be created automatically in the folder where the previous "LOG" file was located.
If it does not works, please let me know.
Akin Adurosakin
Nigeria
create a new project BLNK (blank).
then u should find a file BLNKLOG.p3
if ur project that u wnat to remover the relationship is ABCD, you can delete (or rename just to be safe) ABCDLOG.p3
Copy BLNKLOG.p3 as the new ABCDLOG.p3
That should work...
It worked for me when i remove all resources using same method for ????RES.p3
Thank you, Paco
Alternatively, a colleague just advised me that after exporting to a dbf file - insert a new column called Delete - then populate with the letter L - finally, import the data.
Much appreciated.
Paul
You can try through export/import tools. You can first export to a dbf file your logs, then open in excel and emptying them and finally import again. The result will be no log at your schedule.
Paco