after resources allocation is OK... set to Fixed Work.
reason: with Fixed Work... any change to duration will recalc the units required to achieve the Total Work prev calc. and vice-versa chg to units required will recalc duration to achieve the Total Work prev calc.
as for alvin,
when u assign the resource what was the total work? 40hrs?
if the total hrs as ur expect is supposed to be 10hrs, make sure u do not assign 100% (1 person)
because duration = 5 @ 8hrs per day
assigning 1 person fulltime = 5 x 8 = 40hrs Total Work
so if u estimate Total Work = 10hrs
it means u need only 25% of the input (= 0.25 unit of 25%) depend on ur setting for resource unit
i.e u assign 0.25 Designer or 25% Designer
that would give u Total Work 10hrs and later when u progress the work, the actual work should be 10hrs
If you input a resource onto a FIXED DURATION task, it will automatically assume that the resource is working at 100% for the duration of that activity. Therefore, if you then amend the % Complete to show 100%, it will convert the scheduled hours to actual hours. In order to avoid this, you need to split-screen (show RESOURCE WORK form at the bottom of the screen), input the resouce name and then input the scheduled hours. Only then should you click "OK". When you amend the task to 100% complete, it will convert your 10 scheduled hours to 10 actual hours, appropriately spread across the duration.
If you try doing it any other way round, the gantt bar will probably show lots of little dots.
Its always a pain in the bum, but if you input the data in the correct sequence, you will get the correct results.
On a FIXEd WORK task, the "Effort Driven" checkbox cannot be de-activated.
NOTE OF CAUTION: The intepretation and use of the "FIXED XXX" can be cause for confusion, especially when trying to change resource, duration, units or when re-scheduling uncompleted work. The results are never quite what you expect.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
more experience with msp...
what i normally do...
during initial planning... set to Fixed Duration.
after schedule is OK. assign resources.
after resources allocation is OK... set to Fixed Work.
reason: with Fixed Work... any change to duration will recalc the units required to achieve the Total Work prev calc. and vice-versa chg to units required will recalc duration to achieve the Total Work prev calc.
as for alvin,
when u assign the resource what was the total work? 40hrs?
if the total hrs as ur expect is supposed to be 10hrs, make sure u do not assign 100% (1 person)
because duration = 5 @ 8hrs per day
assigning 1 person fulltime = 5 x 8 = 40hrs Total Work
so if u estimate Total Work = 10hrs
it means u need only 25% of the input (= 0.25 unit of 25%) depend on ur setting for resource unit
i.e u assign 0.25 Designer or 25% Designer
that would give u Total Work 10hrs and later when u progress the work, the actual work should be 10hrs
Hi all,
Another way is to display your custom form. Select View-> Toolbars-> Custom Form
Click Cost Tracking or Work Tracking Icon
If used Cost Tracking change Work to correct hrs, % work complete to 100% and 0% on duration % complete and click OK.
If used Work Tracking change Total to correct hrs, % complete to 100 and 0% on duration % complete and click OK.
Note: Make sure that duration % complete = 0% otherwise MSP automatically calculate the new hrs/ original hrs as duration % complete.
It’s better to use this custom form especially if you have multiple resources on one task to adjust.
Regards,
Rodel
Alwin,
If you input a resource onto a FIXED DURATION task, it will automatically assume that the resource is working at 100% for the duration of that activity. Therefore, if you then amend the % Complete to show 100%, it will convert the scheduled hours to actual hours. In order to avoid this, you need to split-screen (show RESOURCE WORK form at the bottom of the screen), input the resouce name and then input the scheduled hours. Only then should you click "OK". When you amend the task to 100% complete, it will convert your 10 scheduled hours to 10 actual hours, appropriately spread across the duration.
If you try doing it any other way round, the gantt bar will probably show lots of little dots.
Its always a pain in the bum, but if you input the data in the correct sequence, you will get the correct results.
HTH
James.
Alwin,
its not an easy or quick way of doing it, but you could have a try:
display Task Usage (or Resource Usage),
display Actual Work
key in the actual amount of work by day or week (depending the Time Scale zoom)
key in the value 100% for the task % complete
delete the additional amount of work MSP insists to enter after the task finish date
it would take a macro to automatize this process
Alexandre
I hope somebody will have a better idea, I am interested in
I meant: the "Effort Driven" checkbox is dimmed, and automatically set to "Yes", I meant you cannot activate / de-activate it
James is right, undrestanding Task Type in MS Project is worth the price of a good training session with a good instructor.
Alexandre
Correction to Alexandres post.
On a FIXEd WORK task, the "Effort Driven" checkbox cannot be de-activated.
NOTE OF CAUTION: The intepretation and use of the "FIXED XXX" can be cause for confusion, especially when trying to change resource, duration, units or when re-scheduling uncompleted work. The results are never quite what you expect.
James
Alistair,
1. Duration fixed regardless of amout of hours and resourece numbers: set the task type as "Fixed Duration" and uncheck the "Effort driven" box
2. Hours fixed regardless of duration and manpower: set the task type as "Fixed Work"; "Effort driven" will automatically be desactivated.
Any decent book or training material on MS Project (any version since MSP 98) explains that set-up.
All the best,