I don’t know if this works in other versions but in in Primavera version 5.0 you just select all the activities where you want to remove the relationships, you copy them and paste them in the same project. When you click paste the screen appears with what you want to paste, so you deselect relationships and click ok.
Then you get a copy of all your activities but without the relationships. Now you can delete the original activities that still have relationships.
Thanks a lot for your extensive help and it works very well. I struggled a lot before due to unable to recall the reserve letter/word "S". and thanks for your additional information on "A","R" and "L".
Im thinking of P3e on Export where "D" is the delete flag. You should be using "S" instead of "D" in P3.1 to delete activity relationship.
Below are the step to make the things clear.
To delete data in Lotus 1-2-3 or dBASE
Follow these steps to delete the activity ID, resource name or designator, cost account, or relationship type from a spreadsheet or dBASE file; delete or modify all other types of data directly.
1) Export the data to be deleted from P3.
2) Create a new column in Lotus 1-2-3 or add a new field in dBASE. The column or field width must be at least one character. The specific location in the file is unimportant.
3) Name the range Delete using the Range Name command in Lotus 1-2-3, or name the field Delete in dBASE.
The field must be designated as a text range name in Lotus 1-2-3 and as a character field in dBASE.
4) Specify the one-character code in the newly added column or field to delete specific activity data. Leave the cell or field blank for any activities that are unchanged or that contain new or updated data.
A - deletes all data for that activity ID.
R - deletes resources for that activity ID.
L - deletes log records for that activity ID.
S - deletes the relationship for that activity ID.
5) Add any new data to replace the deleted data items. To add or delete relationship types, the activity ID, successor, and relationship type must also exist in the file. Change the relationship lag only if a lag value not equal to zero already exists.
Note: If you are using DBF extension make sure to include into the range name "Database" the column that you added otherwise you will lose your data when save back to DBF extension.
Hope this help. Please let me know the result so I can help you further.
I have introduced another column (DELETE) in Excel(before that i exported the successor relationship from Tools->ProjectUtility) next to the REL column, then typed D under the DELETE column but nothing happens in the P3 when i import that file. Could you please help me further?.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Export it into primavera P5 you can revomed it easily. then i suggest to leave p3 it will become obsolete soon
I don’t know if this works in other versions but in in Primavera version 5.0 you just select all the activities where you want to remove the relationships, you copy them and paste them in the same project. When you click paste the screen appears with what you want to paste, so you deselect relationships and click ok.
Then you get a copy of all your activities but without the relationships. Now you can delete the original activities that still have relationships.
Good luck.
No worries mate, that what PP are for!
Dear Rodel,
Thanks a lot for your extensive help and it works very well. I struggled a lot before due to unable to recall the reserve letter/word "S". and thanks for your additional information on "A","R" and "L".
Cheers!!!
Daya
Sorry Dayanidhi,
Im thinking of P3e on Export where "D" is the delete flag. You should be using "S" instead of "D" in P3.1 to delete activity relationship.
Below are the step to make the things clear.
To delete data in Lotus 1-2-3 or dBASE
Follow these steps to delete the activity ID, resource name or designator, cost account, or relationship type from a spreadsheet or dBASE file; delete or modify all other types of data directly.
1) Export the data to be deleted from P3.
2) Create a new column in Lotus 1-2-3 or add a new field in dBASE. The column or field width must be at least one character. The specific location in the file is unimportant.
3) Name the range Delete using the Range Name command in Lotus 1-2-3, or name the field Delete in dBASE.
The field must be designated as a text range name in Lotus 1-2-3 and as a character field in dBASE.
4) Specify the one-character code in the newly added column or field to delete specific activity data. Leave the cell or field blank for any activities that are unchanged or that contain new or updated data.
A - deletes all data for that activity ID.
R - deletes resources for that activity ID.
L - deletes log records for that activity ID.
S - deletes the relationship for that activity ID.
5) Add any new data to replace the deleted data items. To add or delete relationship types, the activity ID, successor, and relationship type must also exist in the file. Change the relationship lag only if a lag value not equal to zero already exists.
Note: If you are using DBF extension make sure to include into the range name "Database" the column that you added otherwise you will lose your data when save back to DBF extension.
Hope this help. Please let me know the result so I can help you further.
Regards,
Rodel
I have introduced another column (DELETE) in Excel(before that i exported the successor relationship from Tools->ProjectUtility) next to the REL column, then typed D under the DELETE column but nothing happens in the P3 when i import that file. Could you please help me further?.
Yes...just type D on the last column/ delete flag on all activity relationship you need to delete.
Cheers,
Rodel
Is there any keyword for activity relationship to delete from Excel import option?.
Try RA/ Excel Utilities. Easy like magic.
Regards,
Rodel