Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I took time off to study this Issue.
I reviewed Primavera knowledgebase & found that they have an internal field called "Schedule Curve % Complete"
But I do not see this field in my field selection list , say when I use the Columns selection in the activities window.
Is there a way to get this displayed in my column for each activity?
For ref. see Solution ID 20021220165416 Part 2)How is "Planned Value" calculated for activities with resource curves.
BCWS="Scheduled Curve % Compl"*BAC
Romo
In that case please check your Plan Start Date and Plan finish date at the activity level
If you dont mind, please send me the xer file and I can verify the project
Alex
Thanks Alex.
I defined my resource as non-labour.
I do update the following.
Actual % manual update ( % Progress.-Physical), RDU
Also I run a global change to calculate & update Actual resource qty & remaining qty based on % ( I have delinked automatic % vs. RDU).
I am not sure what you mean by link actual to Project level?
Thie Issue is getting the Plan % correct.
"Schedule %" field displays correct value at WBS Band. But at Activity level it is still based on duration ie.
Plan % = (Status date-BL Start)/(BL Finish - BL Start)
Actually what I need is BL Resource Qty / BQ as a percent (Pick from curve)
I could not search % rollup as some admin error in the forum
regards,
Rama
Rama
My question is
Is your resource is Labor or Material or non material?
When you progress your activity do you enter any actual value?
Did you link your actual with progress in the project level?
If you do a search on one of the topic call % rollup I had explain how P3e calculate physical progress and what are the rule of thrumb.
Cheers
Alex