The way you replied seems impolite to me and I couldnt get it. Thanks anyway.
Back to the weni question, it would be happen and u really need further study on site status...u can play aroud with lag rite???? so what is the main problem....for the hammock activities suitable for summary of activities...as highlighted before by alex....
so weni u got what i really meant here???
Also not to forget u need to choose " Hammock" in the Activity Type for that activity to be a hammock for pe to have SS ad se to have FF
Weni
Sound like a hammock activity (summary) to me for Activity No1
That way it will show the earliest start date of a group of activity and latest finish date.
Cheers
Alex
Another good reason to have both a SS and FF relationship is so the successor wont finish before the Predecessor finishes.
Thanks Mr. Dayan. You really of big help to everybody.
Cheers!!!
Weni
Hi Weni,
you can have SS and FF relationship to the predecessor as well successor. the main reason to have FF rel will remove open end to the pred/succ. in your case. or else you will not get any impact during update, if there is any delay in the completion of pred. activity. it depends on the situation to use it.
HTH
Daya