ACTIVITY LINKING?

W
Weni Samson 👤 Member for 19 years 6 months
W
Weni Samson 👤 Member for 19 years 6 months

The way you replied seems impolite to me and I could’nt get it. Thanks anyway.

I
Izam Zakaria 👤 Member for 20 years

Back to the weni question, it would be happen and u really need further study on site status...u can play aroud with lag rite???? so what is the main problem....for the hammock activities suitable for summary of activities...as highlighted before by alex....



so weni u got what i really meant here???

G
Gilbert Liu 👤 Member for 23 years

Also not to forget u need to choose " Hammock" in the Activity Type for that activity to be a hammock for pe to have SS ad se to have FF

A
Alex Wong 👤 Member for 23 years 3 months

Weni



Sound like a hammock activity (summary) to me for Activity No1



That way it will show the earliest start date of a group of activity and latest finish date.



Cheers



Alex

D
David Andreotti 👤 Member for 20 years 11 months

Another good reason to have both a SS and FF relationship is so the successor won’t finish before the Predecessor finishes.

W
Weni Samson 👤 Member for 19 years 6 months

Thanks Mr. Dayan. You really of big help to everybody.

Cheers!!!



Weni

D
Dayanidhi Dhandapany 👤 Member for 23 years 2 months

Hi Weni,



you can have SS and FF relationship to the predecessor as well successor. the main reason to have FF rel will remove open end to the pred/succ. in your case. or else you will not get any impact during update, if there is any delay in the completion of pred. activity. it depends on the situation to use it.



HTH



Daya

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts