LEVELLING OF RESOURCE

J
Jorge Taguinod 👤 Member for 23 years

You can run a Global Change to automatically constrain the leveled early start dates:



Create a new Global Change statement and in the Then area, write:



SNE EQ ES



This should work.



regards,



Jorge Taguinod

M
Martin Polack 👤 Member for 25 years

...or maybe you may make a copy of the "resource levelled" scheduled and use it as a Target 1 (or 2). Then you can prepare a layout comparing that Target against your current schedule.

S
Steven Oliver 👤 Member for 23 years 8 months

Try creating a custom data item to hold the levelled value of early start, and after re-scheduling set the early start constraint equal to the custom data item

Featured Partner

Top Posters

Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts