I agree to both solutions... either global change or exporting it to excel will do... just choose which one you are more comfortable/confident using...
for me, i will enter the resource and curve type in one activity. then export this activity to WK1 (selecting fields Act ID, Des, OD, RES, Units, etc.)
Then in open up this WK1 file in excel, eneter the Act ID for the activities i want to assign with this resource.
copy paste the resource data to these other activities, modify the units per day (or budget qty) as necessary.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I agree to both solutions... either global change or exporting it to excel will do... just choose which one you are more comfortable/confident using...
good luck!
for me, i will enter the resource and curve type in one activity. then export this activity to WK1 (selecting fields Act ID, Des, OD, RES, Units, etc.)
Then in open up this WK1 file in excel, eneter the Act ID for the activities i want to assign with this resource.
copy paste the resource data to these other activities, modify the units per day (or budget qty) as necessary.
Finally import this file back in to P3.
Voila! Done...
Dear
The same simple solution
global change you can assign the curve type with the same methode.
Well Christian
i have added the resource to the activites but what about the curve, units per day ?
soory but i need this too
thanx
sami
thanks Christian
i mworking on that now
i tell you if any probs came up
sami
Sami
the global change is a helpful feature....
hth
Christian