displaying total float for completed activities!!
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
This is actually not a ‘bug,’ just a perceived one. Starting with Version 5, Primavera stopped deleting the early and late dates stored in the database for actual activities It comes as a surprise to everyone but the software industry that completed activities also have ‘float.’
What Primavera forgot to do in their P5 release was to blank out the float column for completed activities. This caused quite a stir in the Users’ World as they were not used to seeing completed activities with float. Very soon after the release of P5, Primavera released Service Pack 1 that corrected this ‘error’ by not printing the float for completed activities. The values still exist in the database, they just are not shown anymore using SP1.
Hello all,
Is SP2 for P5 solving this bug?
Regards.
Marcio Eduardo.
OOPS - I have not made clear that it is "retained logic" that exhibits this problem "progress override" and "actual dates" do not.
its a known "bug". If you schedule using "progress override" or "actual dates" rather than "retained logic" - you find these selections under scheduling options. PO and AD do dreadfull things to your schedule if you have out-of-sequence progress - but thats the only issue.
I forgot to say that i use primavera v5
David,
Thanks a lot