I cannt see what you will have to gain by using the Resources driving optiion in P3. As all your ODs will be calculated from the imported manhours / mixed crew sizes.
Would you not be better to apply it to only any critical resources that you may have.
Thank you for all the response. I will explain my normal way of planning (which initially in MSP, I use almost the
same method).
PLEASE CORRECT/NOTIFY ME IF IM WRONG.
My planning in hours as the jobcards is detailed by manhours.
For each resource in an activity, I will set the BQ & UPT.
(BQ = Total MHrs for that resource, UPT = Resource (e.g. 1 men/2 men Rigger) required for each hour).
The duration (OD) of an activity will be determine by the longest Duration between all resource.
For this I will set all resources as DRIVING.
Im doing it this way because this is the normal way I did in MS Project (minus the driving/non-driving).
Majority of the data are ky in by using MS Excel (Lotus - P3 import/export)
From my understanding, as an offshore work where are men, eqpt, materials are available before work all my resources should be DRIVING. Is that Correct?
in P3 you can set up your resource availability / calendars and by changing the activity TYPE you will make p3 calculates and decide about the critical one. (the driving one) then you will have the correct duration.
Driving/no driving resource is a general term in scheduling.
to finish a task, e.g. to install piping, you may need crane,pipe, welder... , all these you need to finish the task are considered resource, which resource control the duration of the task,then the resource is consider as driving.
which is driving depends on the site condition, if you have problem with pipe fabrication/delivery,it can be a driving resource. if you have enough piping, but few welder, then welder can be driving.
So different project has different driving resource, even they are same type,size...
Your Driving resources will depend on what your critical resouces turns out to be when you compare your planned planhours against what you have physically available.
Most hook-ups I have worked on we always seem to have a problem with Pipe Welders(6G) who weld the exotic materials i.e. Kunifer, Stainless, Moly etc.
Other key trades are the High Voltage Cablers/Terminators,(need to Certifiied) along with Electricians for Termination/Testing work (latter not a case of numbers of electricians but access to the termination cabinets).
Another one to watch out for is Pipework Pressure testing labour along with NDE/NDT testing, not because of the manhours etc but the safety restrictions that will close off parts of the platform when they are working.
The final one to watch out for are the Commissioning Technicians, all types i.e Electro, Instrumennts, Mechanical, Telecomms etc.
The general trades i.e. plate workers, plate welders, Pipe fitters, Insulators, Scaffolders etc should not cause you many problem as long as their is a sufficient supply afailable.
One thing I would warn you is to avoid letting P3 loose to carry out scheduling of labour, as your schedules produced can look very "strange". You have to play about with the scheduling criteria to get it to produce a workable plan. I tend to just use the network logic and apply dates that P3 call "Constrains" then hopefully I can produce a resonable histogramme.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi,
I cannt see what you will have to gain by using the Resources driving optiion in P3. As all your ODs will be calculated from the imported manhours / mixed crew sizes.
Would you not be better to apply it to only any critical resources that you may have.
Regards
John
Good day to all
Thank you for all the response. I will explain my normal way of planning (which initially in MSP, I use almost the
same method).
PLEASE CORRECT/NOTIFY ME IF IM WRONG.
My planning in hours as the jobcards is detailed by manhours.
For each resource in an activity, I will set the BQ & UPT.
(BQ = Total MHrs for that resource, UPT = Resource (e.g. 1 men/2 men Rigger) required for each hour).
The duration (OD) of an activity will be determine by the longest Duration between all resource.
For this I will set all resources as DRIVING.
Im doing it this way because this is the normal way I did in MS Project (minus the driving/non-driving).
Majority of the data are ky in by using MS Excel (Lotus - P3 import/export)
From my understanding, as an offshore work where are men, eqpt, materials are available before work all my resources should be DRIVING. Is that Correct?
Cheers
Redzuan
dear all,
in P3 you can set up your resource availability / calendars and by changing the activity TYPE you will make p3 calculates and decide about the critical one. (the driving one) then you will have the correct duration.
Regards,
Im not fimilar with oil/gas.
Driving/no driving resource is a general term in scheduling.
to finish a task, e.g. to install piping, you may need crane,pipe, welder... , all these you need to finish the task are considered resource, which resource control the duration of the task,then the resource is consider as driving.
which is driving depends on the site condition, if you have problem with pipe fabrication/delivery,it can be a driving resource. if you have enough piping, but few welder, then welder can be driving.
So different project has different driving resource, even they are same type,size...
HTH
Hi
Your Driving resources will depend on what your critical resouces turns out to be when you compare your planned planhours against what you have physically available.
Most hook-ups I have worked on we always seem to have a problem with Pipe Welders(6G) who weld the exotic materials i.e. Kunifer, Stainless, Moly etc.
Other key trades are the High Voltage Cablers/Terminators,(need to Certifiied) along with Electricians for Termination/Testing work (latter not a case of numbers of electricians but access to the termination cabinets).
Another one to watch out for is Pipework Pressure testing labour along with NDE/NDT testing, not because of the manhours etc but the safety restrictions that will close off parts of the platform when they are working.
The final one to watch out for are the Commissioning Technicians, all types i.e Electro, Instrumennts, Mechanical, Telecomms etc.
The general trades i.e. plate workers, plate welders, Pipe fitters, Insulators, Scaffolders etc should not cause you many problem as long as their is a sufficient supply afailable.
One thing I would warn you is to avoid letting P3 loose to carry out scheduling of labour, as your schedules produced can look very "strange". You have to play about with the scheduling criteria to get it to produce a workable plan. I tend to just use the network logic and apply dates that P3 call "Constrains" then hopefully I can produce a resonable histogramme.
Regards
John