Schedule Variance Procedures

P
Peter Holroyd 👤 Member for 21 years 1 month

key data to be derived from the schedule is



1 SPI performance on an accum and period basis of current v baseline programmes - this gives the history then look forward by

2 SPI Index to Completion - this is the improvement required to finish the job on time (assuming you are behind)from which you can see whether it is realistic

3 Print out the top (5 ?) critical paths on the project and make sure they are sensible and everyone knows which are the current activitites on these critical paths

4 then as a test to see if you programme is getting more critical try a Float Trend Analysis graph

5 a simple Principle line would be nice but most software doesn’t support this



Hope this helps

Forum Sponsor

Top Posters

Mohammed Netarwala
12 posts
Moahmed
0 posts
S Z
4 posts
Iftikhar Awan P.Eng.
19 posts
ahmad rashidi
4 posts
paulciszewski
0 posts
Catalin Suditu
11 posts
Laraib Fatima
0 posts
Adrian Fletcher
12 posts
GeoVe
0 posts