Schedule Variance Procedures

P
Peter Holroyd 👤 Member for 21 years

key data to be derived from the schedule is



1 SPI performance on an accum and period basis of current v baseline programmes - this gives the history then look forward by

2 SPI Index to Completion - this is the improvement required to finish the job on time (assuming you are behind)from which you can see whether it is realistic

3 Print out the top (5 ?) critical paths on the project and make sure they are sensible and everyone knows which are the current activitites on these critical paths

4 then as a test to see if you programme is getting more critical try a Float Trend Analysis graph

5 a simple Principle line would be nice but most software doesn’t support this



Hope this helps

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts