Hi sir
May, I can help you, I think you have limited resouce and you want to know how we can this resource for activities, you should do leveling for your resources, you can select "Tools" and then "level" next go in tab of resource. just you shall know leveling to make a new schedule based on logical relationship of activities.
I hope the above is clear.
Our requirement is only to use one loader for these two activties then how we assign loader for these two activites so that net result should come out as one loader?
It is because of the same dumper assigned to work on the same duration for two concurrent activities, so P3 calculates 2 dumpers.