Resource Computation

M
Morteza Jafari 👤 Member for 22 years 10 months

Hi sir

May, I can help you, I think you have limited resouce and you want to know how we can this resource for activities, you should do leveling for your resources, you can select "Tools" and then "level" next go in tab of resource. just you shall know leveling to make a new schedule based on logical relationship of activities.

I hope the above is clear.

S
Shahzad Munawar 👤 Member for 22 years 11 months

Our requirement is only to use one loader for these two activties then how we assign loader for these two activites so that net result should come out as one loader?

F
Forum Guest 👤 Member for 17 years 4 months

It is because of the same dumper assigned to work on the same duration for two concurrent activities, so P3 calculates 2 dumpers.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts