PD 1594 applies and in combination with the consultant prepared contract patterned after FIDIC. THere is an escalation clause but it applies to local (Peso) component of the contract only. It cannot apply to the foreign portion as stated in the said clause.
THe point I raised was that the project performance have been moved to a period of higher prices compared with the time when the contract should have been performed according to the original schedule. IT was already established that delay was due to the owner and a separate contract clause exists - that during such case, the Engineer and the COntractor will determine the cost incurred by the COntractor due to this delay. The claim related to delay covers the local component of the contract only and the foreign portion cannot be compensated on the basis of existing clause (in PD1594) which states that escalation will only apply to the local portion.
I was thinking maybe it would be more appropriate to say that the an additional cost was incurred due to price escalation (of foreign portion or imported materials/services). THe PD1594 clause for price escalation is indeed applicable only to local portion in the sense that the formula established would use price indices (or K factor) here in the Philippines. As to the foreign portion, or materials/services procured outside the Philippines, the escalation rate from country of source should be the basis.
Im just curious, what type of contract are you using is it PD 1594 or FIDIC? I think in both contracts, escalation can be claimed especially in PD 1594 which outlines specifically how you can compute escalation charges.
On the issue of Delay by the owner, please note that an EOT claim is entirely different from escalation claim. Trying to fit in the merits of your claim combining the two issues to me, would be hard to prove. Please note also that in PD 1594 regarding EOT also, you can only be granted the time component but it is not compensable, meaning you can not claim for EOT with cost.
Assuming your claim is very obvious but without clear contractual basis, the dilemma still lies on the one approving the claim.
On Mercy Claim, is it really not possible to use as basis an applicable clause in the contract, which states that "Failure of Owner ..." entitles the COntractor an additional cost to the Contract? Assuming a project has been delayed due to owner-cause delay, can we not rely on this applicable clause, which I think is commonly included in a construction contract. I stated that it can be viewed as mercy claim with contractual basis because there is an available provision although it is being contradicted by another contract clause regarding escalation. But can we use the term "additional cost" rather than "escalation cost" to dis-relate it to the escalation clause?
Almost all conditions of contrats prepared by the owners do not allow for price escalation and subsequent legislation.
A common problem in my country now is the effect of the worldwide increase in the prices of steel reinforcement, that reached up to 35% compared to a year ago (around $100 per ton).
Considering that any building project can easily contain 3000 tons of steel, the losses incurred by contractors were very heavy for any contractor to bear.
Since these losses cannot be claimed under the contract, I was looking for a way out in the governing common laws.
In some legal systems, there is a theory of the unforeseen circustances, which allows the contractor for compensation despite the existence of a clear clause in the contract stating the opposit. The concept behind this theory is that a contractor can bear a certain degree of risk, but when the price fluctuation causes *excessive damages*, then the economical balance of the contract established at the start of the contract, is destabilized.
I am still working on this issue. If anybody is interested, I can keep you updated.
In addition to the last thread, "I-hope-you-understand-our-situation" approach is also called mercy claim. which may or may not be granted because it may place the other party in dilemma to approve a claim without a contractual basis.
I am handling a similar case in a railway project. We are seeking a price escalation for the foreign component of the project cost. The contract explicity stated that no price escalation will be allowed for foreign portion. But my position is to call the claim an additional cost incurred by the Contractor due to "Failure to give Possession of Site", which should be added to the contract price. THe method of calculation for additional cost would be cost increment due to escalation. Its still a debatable issue because there are contradicting clauses. I believe that its approval relies on a negotiating environment between parties, the Contractor should undertake a sort of mercy claim with contractual basis. There is no doubt that COntractor has incurred cost and the Owner may recognize the Contractors predicament if the claims negotiator could impart an "I-hope-you-understand-our-situation" approach.
In your case, where no contract has been provided for escalation, try using the above approach.
Yes there are some justification which can be made such as the principle of quantum maruit among others. But if the client will have his hands tied on the contract especially for government as client, which is in my case 8 months ago, the ultimate remedy to my mind is arbitration which is very tedious and time consuming. Not to mention it is also an irritant to some which may cause you to lose a client.
You are true in saying that Escaltion claim can not be entertained without Explicit Clause in Contract. It may only be entertained in case of Clause or by conduct but to my understanding there will surely exist a legal remedy for such type of cases
May you or anyone refer such judgements on this type of case?
You may want to view one of the post I made regarding "contract provision not stated" in this forum category.
It is really hard to claim something which is not explicitly stated in a contract. You may try to file a claim but if your client would immediately state that what youre claiming is not written in the contract, it would be quite hard to deal with that. Sometimes we call this mercy claim.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Kabayan Rex :-)
PD 1594 applies and in combination with the consultant prepared contract patterned after FIDIC. THere is an escalation clause but it applies to local (Peso) component of the contract only. It cannot apply to the foreign portion as stated in the said clause.
THe point I raised was that the project performance have been moved to a period of higher prices compared with the time when the contract should have been performed according to the original schedule. IT was already established that delay was due to the owner and a separate contract clause exists - that during such case, the Engineer and the COntractor will determine the cost incurred by the COntractor due to this delay. The claim related to delay covers the local component of the contract only and the foreign portion cannot be compensated on the basis of existing clause (in PD1594) which states that escalation will only apply to the local portion.
I was thinking maybe it would be more appropriate to say that the an additional cost was incurred due to price escalation (of foreign portion or imported materials/services). THe PD1594 clause for price escalation is indeed applicable only to local portion in the sense that the formula established would use price indices (or K factor) here in the Philippines. As to the foreign portion, or materials/services procured outside the Philippines, the escalation rate from country of source should be the basis.
Regards
[duplicate post]
Hi Carolina kabayan,
Im just curious, what type of contract are you using is it PD 1594 or FIDIC? I think in both contracts, escalation can be claimed especially in PD 1594 which outlines specifically how you can compute escalation charges.
On the issue of Delay by the owner, please note that an EOT claim is entirely different from escalation claim. Trying to fit in the merits of your claim combining the two issues to me, would be hard to prove. Please note also that in PD 1594 regarding EOT also, you can only be granted the time component but it is not compensable, meaning you can not claim for EOT with cost.
Assuming your claim is very obvious but without clear contractual basis, the dilemma still lies on the one approving the claim.
On Mercy Claim, is it really not possible to use as basis an applicable clause in the contract, which states that "Failure of Owner ..." entitles the COntractor an additional cost to the Contract? Assuming a project has been delayed due to owner-cause delay, can we not rely on this applicable clause, which I think is commonly included in a construction contract. I stated that it can be viewed as mercy claim with contractual basis because there is an available provision although it is being contradicted by another contract clause regarding escalation. But can we use the term "additional cost" rather than "escalation cost" to dis-relate it to the escalation clause?
[duplicate post]
I am facing the same problems:
Almost all conditions of contrats prepared by the owners do not allow for price escalation and subsequent legislation.
A common problem in my country now is the effect of the worldwide increase in the prices of steel reinforcement, that reached up to 35% compared to a year ago (around $100 per ton).
Considering that any building project can easily contain 3000 tons of steel, the losses incurred by contractors were very heavy for any contractor to bear.
Since these losses cannot be claimed under the contract, I was looking for a way out in the governing common laws.
In some legal systems, there is a theory of the unforeseen circustances, which allows the contractor for compensation despite the existence of a clear clause in the contract stating the opposit. The concept behind this theory is that a contractor can bear a certain degree of risk, but when the price fluctuation causes *excessive damages*, then the economical balance of the contract established at the start of the contract, is destabilized.
I am still working on this issue. If anybody is interested, I can keep you updated.
In addition to the last thread, "I-hope-you-understand-our-situation" approach is also called mercy claim. which may or may not be granted because it may place the other party in dilemma to approve a claim without a contractual basis.
Shazad,
I am handling a similar case in a railway project. We are seeking a price escalation for the foreign component of the project cost. The contract explicity stated that no price escalation will be allowed for foreign portion. But my position is to call the claim an additional cost incurred by the Contractor due to "Failure to give Possession of Site", which should be added to the contract price. THe method of calculation for additional cost would be cost increment due to escalation. Its still a debatable issue because there are contradicting clauses. I believe that its approval relies on a negotiating environment between parties, the Contractor should undertake a sort of mercy claim with contractual basis. There is no doubt that COntractor has incurred cost and the Owner may recognize the Contractors predicament if the claims negotiator could impart an "I-hope-you-understand-our-situation" approach.
In your case, where no contract has been provided for escalation, try using the above approach.
Shahzad,
Yes there are some justification which can be made such as the principle of quantum maruit among others. But if the client will have his hands tied on the contract especially for government as client, which is in my case 8 months ago, the ultimate remedy to my mind is arbitration which is very tedious and time consuming. Not to mention it is also an irritant to some which may cause you to lose a client.
Regards,
Se
Mr. Leon:
You are true in saying that Escaltion claim can not be entertained without Explicit Clause in Contract. It may only be entertained in case of Clause or by conduct but to my understanding there will surely exist a legal remedy for such type of cases
May you or anyone refer such judgements on this type of case?
Shahzad,
You may want to view one of the post I made regarding "contract provision not stated" in this forum category.
It is really hard to claim something which is not explicitly stated in a contract. You may try to file a claim but if your client would immediately state that what youre claiming is not written in the contract, it would be quite hard to deal with that. Sometimes we call this mercy claim.
Regards,
Se