Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
thank you sir,
am finally able to break the Da Vinci Code of my project
Cheers
jatin
Thankyou Masood. I was being lazy and hoped that he himself would discover how to do this. It should be in the HELP file.
James :-)
now proceed as follows
go to TOOL/TRACKING?UPDATE PROJECT/
select o RESCHEDULE UNCOMPLETED WORK TO START __*_____
* date of progress
finally select O ENTIRE PROJECT
goodluck
MASOOD AHMED
Jatin,
After inputting progress, always remember to "Reschedule Uncompleted Work". If you do not do this, then the project end-date will not change.
James.
you can find this information from menu:
Project - porject information... - finish date
or you can show the porject summary bar, it also give you the end date
Precisely Sir,
thats what i am searching for, i.e the Updated End Date of the Project.
In my case, Some Activities have crossed their Basline End Date, and the Actual End Date is greater than the Baseline End Date.
So i am interested in knowing, if this has caused any change to the Scheduled End Date of the project.
Would this be reflected in the Project Information (Statistics) part or would it be reflected some place else?
Because as of now, nothing is being refleted in Proj Info (Stats) barring the Baseline Dates.
Awaiting your valuable comments
Regards
Jatin
after saving baseline , & progress input , you might have a same end date as of base line or another updated end date depending upon teh followinf
A- PLAIN SCHEDULING
1. dependin upon link/relationship
2. actual progress input faster /slower than baseline
3. any constraint date
B - SCHEDULING WITH RESOURCE LOADING
1. in case of efforts driven tsak , availabblity of res. as per relevent res. calander ( if any )
2. also depending on link & res. availability , later time of among both
regds
M . FAROOQI