Projected End Date of Project in MSP

J
jatin mamman 👤 Member for 20 years 3 months

thank you sir,



am finally able to break the Da Vinci Code of my project





Cheers



jatin

J
James Griffiths 👤 Member for 20 years

Thankyou Masood. I was being lazy and hoped that he himself would discover how to do this. It should be in the HELP file.



James :-)

M
Masood Ahmed Farooqi 👤 Member for 20 years 4 months

now proceed as follows



go to TOOL/TRACKING?UPDATE PROJECT/

select o RESCHEDULE UNCOMPLETED WORK TO START __*_____



* date of progress



finally select O ENTIRE PROJECT



goodluck



MASOOD AHMED

J
James Griffiths 👤 Member for 20 years

Jatin,



After inputting progress, always remember to "Reschedule Uncompleted Work". If you do not do this, then the project end-date will not change.



James.

Z
Zhang Haixiang 👤 Member for 21 years 1 month

you can find this information from menu:



Project - porject information... - finish date



or you can show the porject summary bar, it also give you the end date

J
jatin mamman 👤 Member for 20 years 3 months

Precisely Sir,

thats what i am searching for, i.e the Updated End Date of the Project.

In my case, Some Activities have crossed their Basline End Date, and the Actual End Date is greater than the Baseline End Date.



So i am interested in knowing, if this has caused any change to the Scheduled End Date of the project.



Would this be reflected in the Project Information (Statistics) part or would it be reflected some place else?

Because as of now, nothing is being refleted in Proj Info (Stats) barring the Baseline Dates.



Awaiting your valuable comments



Regards



Jatin




M
Masood Ahmed Farooqi 👤 Member for 20 years 4 months

after saving baseline , & progress input , you might have a same end date as of base line or another updated end date depending upon teh followinf



A- PLAIN SCHEDULING



1. dependin upon link/relationship

2. actual progress input faster /slower than baseline

3. any constraint date







B - SCHEDULING WITH RESOURCE LOADING



1. in case of efforts driven tsak , availabblity of res. as per relevent res. calander ( if any )



2. also depending on link & res. availability , later time of among both



regds



M . FAROOQI






Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts