Projected End Date of Project in MSP
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
thank you sir,
am finally able to break the Da Vinci Code of my project
Cheers
jatin
Thankyou Masood. I was being lazy and hoped that he himself would discover how to do this. It should be in the HELP file.
James :-)
now proceed as follows
go to TOOL/TRACKING?UPDATE PROJECT/
select o RESCHEDULE UNCOMPLETED WORK TO START __*_____
* date of progress
finally select O ENTIRE PROJECT
goodluck
MASOOD AHMED
Jatin,
After inputting progress, always remember to "Reschedule Uncompleted Work". If you do not do this, then the project end-date will not change.
James.
you can find this information from menu:
Project - porject information... - finish date
or you can show the porject summary bar, it also give you the end date
Precisely Sir,
thats what i am searching for, i.e the Updated End Date of the Project.
In my case, Some Activities have crossed their Basline End Date, and the Actual End Date is greater than the Baseline End Date.
So i am interested in knowing, if this has caused any change to the Scheduled End Date of the project.
Would this be reflected in the Project Information (Statistics) part or would it be reflected some place else?
Because as of now, nothing is being refleted in Proj Info (Stats) barring the Baseline Dates.
Awaiting your valuable comments
Regards
Jatin
after saving baseline , & progress input , you might have a same end date as of base line or another updated end date depending upon teh followinf
A- PLAIN SCHEDULING
1. dependin upon link/relationship
2. actual progress input faster /slower than baseline
3. any constraint date
B - SCHEDULING WITH RESOURCE LOADING
1. in case of efforts driven tsak , availabblity of res. as per relevent res. calander ( if any )
2. also depending on link & res. availability , later time of among both
regds
M . FAROOQI