Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hello all.
Read this other response.
From Primavera:
Define a task activity. P3 schedules a task activity according to
the base calendar assigned to the activity. Designate an
activity as a task activity if you arent assigning resources to the
activity, or if the assigned resources should be scheduled
according to the activitys base calendar; rather than each resource
calendar.
For example, several activities must be done in the week before a new
radio station begins broadcasting. It doesnt matter
whether the resources are available earlier than that week, or
whether they will otherwise be scheduled for time off during
that week--these activities must be scheduled during a specific
timeperiod, and their scheduling controls the scheduling of
their resources.
Define a hammock activity. Use hammocks to monitor the elapsed
beginning-to-end duration of a group of activities. A
hammock duration is the number of days between the beginning of the
first activity and the end of the last one in the
group--not the sum of the activities durations. If several hammocked
activities overlap, the hammocks duration will be smaller
than the combined durations; if large gaps exist between the
activities in the hammock, its duration may be longer.
To set up a hammock activity
1 Display the Predecessors form for the hammock activity.
Define the hammocks predecessors. Specify a start to start
relationship and zero lag for all predecessors to the hammock.
2 Display the Successors form for the hammock activity. Specify
a finish to finish relationship and zero lag for all
successors to the hammock.
3 After you establish the beginning and ending points of the
hammock, calculate the schedule.
Regards.
Marcio Eduardo
Rio de Janeiro - Brazil
Hello Paul and Praves
Thanks a lot.
Regards.
Marcio Eduardo.
Or, to keep it simple.
A hammock summarises task activities (using the criteria provided by Praves)
Hello,
I found one article explained clearly for Hammock
1. P3 calculates the duration of a hammock activity and graphically presents it on the layout
based on the early dates only.
2. For a hammock activity with no progress, P3 calculates a hammock’s duration by the
difference from the earliest early start date of the its predecessor activities to the latest early
finish date of its successor activities. Therefore it has no fixed duration. P3 calculates the
original and remaining durations automatically based on the following formula:
a. Original Duration = (Early Finish Date – Early Start Date)
b. Remaining Duration = Original Duration
3. A hammock should have at least one predecessor and one successor. A hammock without
predecessor starts on the data date, and that a hammock without successor ends on the
project completion date.
4. For a hammock activity in progress, a hammock activity bar starts on the actual date, and
P3 calculates the original and remaining durations, and percent complete automatically
based on the following formula:
a. Remaining Duration = (Early Finish Date – Data Date)
b. Original Duration = (Data Date – Actual Start) + Remaining Duration
c. Percent Complete = (Original Duration – Remaining Duration) / Original Duration
5. A hammock activity can’t drive (push out) any task activities. I often call its behavior like a
“Rubber Band” as it is stretched or compressed according to its successor and predecessor,
not the other way around.
6. If you unlink the remaining duration and schedule percent complete in the Autocost Rules
window, you can manually enter the percent complete for a hammock activity. However,
you absolutely can’t manually enter the original and remaining durations. P3 will overwrite
your inputs.
7. An asterisk mark (*) will always be shown right next to the original and remaining durations
of a hammock activity to denote that the durations are automatically calculated by P3.