Then it is very simple, press Shift F7 and the resource table will appear right at the bottom. Select the time scale and Peak under diplay tab of the table.
I think you are looking for something similar to what the Peak function of P3 did in Reoruce Table. I am also a fan of that and was very upset when it was not found in P3e/c.
Somewhat similar results can be obtained via Spread Options in Resource Spreadsheet. This can be accessed by cliking on Display on rightmost window of Resource Spreadsheet.
In P3e there is no "Spreadsheet Options". What it has is only Spreadsheet Fields which contains only options which are predetermined and we cannot apply any formula to them. Can you please elaborate if I am still at mistake?
you can divide the spreadsheet by right-clicking and chosing "Spreadsheet options" to divide the values by a constant. (intutitive or what!)
Note that this constant CANNOT be based on the hours per day that the resource works, just the number you give it, or the current hours-per day/week in the admin or user preferences. There is no equivalent of P3 3.1s "Peak" setting
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Rashid,
You are right in your saying. But this is true for P3 ver 3.1, while the version which I have is P3e 3.5.1, which is not the same.
Sorry about the mistake, i have used P3e/c 4.0 and 5.0 and have no clue about the version which you are using.
Regards
Rashid
Then it is very simple, press Shift F7 and the resource table will appear right at the bottom. Select the time scale and Peak under diplay tab of the table.
Let me know if thre is still any problem.
Regards
Rashid
Thanks Rashid but I dont have P3e/c. My version is old one (P3e 3.5.1) which does not contain "Spread Options" option.
Ijaz,
I think you are looking for something similar to what the Peak function of P3 did in Reoruce Table. I am also a fan of that and was very upset when it was not found in P3e/c.
Somewhat similar results can be obtained via Spread Options in Resource Spreadsheet. This can be accessed by cliking on Display on rightmost window of Resource Spreadsheet.
Regards
Rashid
I have version 3.5.1 of P3e
Which version of P3e do you have? Its listed under the help pull down
In P3e there is no "Spreadsheet Options". What it has is only Spreadsheet Fields which contains only options which are predetermined and we cannot apply any formula to them. Can you please elaborate if I am still at mistake?
you can divide the spreadsheet by right-clicking and chosing "Spreadsheet options" to divide the values by a constant. (intutitive or what!)
Note that this constant CANNOT be based on the hours per day that the resource works, just the number you give it, or the current hours-per day/week in the admin or user preferences. There is no equivalent of P3 3.1s "Peak" setting