Constraint

Z
Zhang Haixiang 👤 Member for 21 years 3 months

MSP only show date under default setting.

from "Tools" menu click "Options" click "View" tab, under "Date format" choose a format showing date and time.

then you can input date and time in the start/finish column.

this will add start no earlier/finish no earlier constraint.



actually you can directly input e.g. "6/25/06 9:00 am" in start/finish field (or advanced tab )to add constraint

W
W A 👤 Member for 20 years 1 month

more details is requiered, is it a contractual start or not? if it is not in the contract the consultant (or any reviewer) will reject the constrained schedule, the logic must flow.



Anyway, i’ll assume that it is a contractuall constraint, may be the owner will furnish certain planet to the project, Also, the I’ll assume that you know the constraints type, and you need the Must Start On type specifically.



1) double click the activity,

2) click the Advanced tab

3) from the constraint type drop-box select must start on

4) specify date.



click ok



enjoy

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts