It is quite frequent to have new items included in contracts (normaly we call them additionals).
One option for not having them mixed is to create a subproject for each additional. Another option is to create such a structure for the database that you can separte them and measure progress independentl (as well as the overall completion)
Any way you should always make a target for each revision you issue of the plan.
In your example you are right when mentioning the overall progress goes from 33 to 30% (because your project became bigger). This changes should also be reflected in your budget and so on.
If you work in any site you will see that project as actul case, so that i think our working in that program((primavera p3)) must be to find a solution for any case, and with repect to that case for updating of information after you entered a new data
..very easy ,
you can solve by enter the new percent for each acitivity as indivitual case, than enter the remainding date for each case after get schdual new , than you can see the differance
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear Edgar Ariete
Thanks
Dear Yousif,
Im trying to learn to write in Arabic but its all Greek to me.
Maybe you can help me with this one.
regards,
edgar
Hello George
It is quite frequent to have new items included in contracts (normaly we call them additionals).
One option for not having them mixed is to create a subproject for each additional. Another option is to create such a structure for the database that you can separte them and measure progress independentl (as well as the overall completion)
Any way you should always make a target for each revision you issue of the plan.
In your example you are right when mentioning the overall progress goes from 33 to 30% (because your project became bigger). This changes should also be reflected in your budget and so on.
Hope to be any help for you
BR
JMFrade
Hi,
I guess you are right. Thats why its difficult to compare your Target with your Current Plan considering your sample.
If I may add your question, How many Target Plans does a Project needs?
Dear Edgar Ariete
If you work in any site you will see that project as actul case, so that i think our working in that program((primavera p3)) must be to find a solution for any case, and with repect to that case for updating of information after you entered a new data
..very easy ,
you can solve by enter the new percent for each acitivity as indivitual case, than enter the remainding date for each case after get schdual new , than you can see the differance
Ihope advise you by this inforamtion ,
thank you for your reponse
with best best
Engineer : Yousif A.Ayal