Regarding Actual Qty in Activity Column

K
Kannan KG 👤 Member for 20 years 9 months
J
Jackie Gilliland 👤 Member for 21 years 4 months

Hi Kannan



I did a quick check, on my first step below, you could actually load your first column by using a global change rather than to have to load it manually.



Good luck



Jackie Gilliland

J
Jackie Gilliland 👤 Member for 21 years 4 months

Hi Kannan



I can quickly think of a solution to your problem but this is a pretty roundabout way, but should work.



create 3 data code fields.

In the first you will need to manually ad your actual quantity of the resource you would like to measure.



leave other 2 blank.



Now create a global change report with.

If: Leave blank

Then:Col 2 = Col 1 * pct



this will give you a value unfortunatly not divided by 100



Create a 2nd global change

If: Leave blank

Then:Col 3 = Col 2 / 100



This is quite an exercise for what you are looking for, so it depends on how seriously you need to do this. There may be shorter alternatives but this is off the top of my head.



good luck

Jackie Gilliland

R
Razi Khan 👤 Member for 22 years 1 month

Hi Kannan,



Can you elabroate little more with example ?



Razi Khan

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts