Payments schedule

M
Marcio Sampaio 👤 Member for 20 years 7 months

Hi Muhammad,



The project file is too big (more than 7.000 activities - 20 MB).



Regards.



Marcio.

M
MUHAMMAD IQBAL 👤 Member for 20 years 9 months

HI

Marcio Sampaio





I was doing it by % wt Assinment .



so at the end of month wat so ever will be EV same will paided to contactor so very sipmle



can i have your project so that i can reveiw and comments



regards

M
Marcio Sampaio 👤 Member for 20 years 7 months

Thanks Muhammad,



I already did the Payments schedule and it is working. The most difficult thing is to do the links between the activities that generates payments events and the milestones.



I create a diferent project with the milestones - payment events - and integrate with the timeschedule. For the time being, it’s working.



Any opinion??



Regards.



Marcio Eduardo.

Rio de Janeiro - Brazil

M
MUHAMMAD IQBAL 👤 Member for 20 years 9 months

yes it is very nice idea from u

but you will be happy to hear that i have already worked on it.



in Saudia i was been practising



Details can be provided



have fun



iqbal

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts