Thats the problem. Contractos are not working in proper way. And im trying to show them it. But they are sayig that invalid relationships do not affect negative a time schedule.
I simulate it in a small project. And it really doesnt affect. But if the P3e report generate after schedule the project show us a list of invalid relatioships, i think that its is because its a mistake of P3e users.
You are right.Normally, if you schedule in proper way(by defining start milestone in the first place)even P3e also will not allow you to use FF relationship.It will only stays as FF if you change the activity to a start milestone.But as far as negative float is concern, It will be same in both the cases.You can make a small schedule and try to see the difference.
But P3e allow. If u have two activities with FF relationship and, for any reason, u decide to change one of them in a Star Milestone, P3e does not change the FF link. So it becomes in an invalid relationship.
A "Start Milestone" with a FF relationship with a predecessor. "Start Milestone" does not have finish date, so a FF realtionship is invalid. I just want to know how much it affects negative a timeschedule.
You were referring to invalid relationships in you reply.What do you mean by that? Inorder to justify your order you must know which relationships are invalid.It all depends on the type of work you are doing and the sequence of that works.If contractor links activties out of that sequence, those link will be invalid and you can ask them to modify them.
You are the right one to aswer this question as you had developed the plan, the links and activities.The milestones will be affected by all the driving predecessors and to an amount they are being pushed forward to.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Dinesh,
Thats the problem. Contractos are not working in proper way. And im trying to show them it. But they are sayig that invalid relationships do not affect negative a time schedule.
I simulate it in a small project. And it really doesnt affect. But if the P3e report generate after schedule the project show us a list of invalid relatioships, i think that its is because its a mistake of P3e users.
Are u agree??
Regards.
Hi Marcio Eduardo,
You are right.Normally, if you schedule in proper way(by defining start milestone in the first place)even P3e also will not allow you to use FF relationship.It will only stays as FF if you change the activity to a start milestone.But as far as negative float is concern, It will be same in both the cases.You can make a small schedule and try to see the difference.
Thanks & regards
Dinesh
Ok.
But P3e allow. If u have two activities with FF relationship and, for any reason, u decide to change one of them in a Star Milestone, P3e does not change the FF link. So it becomes in an invalid relationship.
Regards.
Marcio Eduardo.
Hi,
P3 does not allow FF or SF relation to a start milestone and hence, you do not have to worry about that.
Thanks & regards
Dinesh
Hi Dinesh,
Thanks for your interest.
Im refering a links like that:
A "Start Milestone" with a FF relationship with a predecessor. "Start Milestone" does not have finish date, so a FF realtionship is invalid. I just want to know how much it affects negative a timeschedule.
Regards.
Marcio Eduardo
Hi,
I am sorry about that.
You were referring to invalid relationships in you reply.What do you mean by that? Inorder to justify your order you must know which relationships are invalid.It all depends on the type of work you are doing and the sequence of that works.If contractor links activties out of that sequence, those link will be invalid and you can ask them to modify them.
Regards
Dinesh
Dinesh,
I didnt do the plan. Im a fiscal of contractors plan.
I asked contractos to modify milestones with invalid relashionships, but i have to justify this order.
Regards.
Marcio Eduardo
Hi,
You are the right one to aswer this question as you had developed the plan, the links and activities.The milestones will be affected by all the driving predecessors and to an amount they are being pushed forward to.
Regards
Dinesh