Youre probably right or there doesnt seem much point in defining the two seperately. It may be a case of partial occupancy is required by the Employer and so it is being used as a form of sectional completion.
As we dont know all the facts, one guess is as good as another!
Andrew is right when he notes that the correct answer is dependant upon the specific wording of the Contract, which is the opening point in my answer below! ;-)
In my experience ‘Beneficial Occupancy’ takes place ahead of Substantial Completion. Substantial Completion is the point at which the Works are considered to be complete and from which LADs would commence, AND at which point the Employer would normally occupy the Works.
If the Employer occupies the Works at the point of Substantial Completion, (which is the normal case) it is difficult to see where the added benefit is. On this basis, I would suggest that Substantial Completion and Beneficial Occupancy cannot be the one and the same thing.
Somewhere between Ronalds and Stuarts answer is the correct answer depending on the contract wording. Both are correct in what they say.
It may be the case that if the ocupancy is of the whole of the works and not just a section then the date of substantial completion and date of beneficial occupancy may be one and the same.
Substantial completion is often (but not always - read the contract) defined as the point at which the Employer starts or could have started to gain benefit from the object being built.
“Substantial Completion” often refers to the point in a project where the Owner is able to use the facility for its intended purpose. This means different things depending upon what type of facility you have in mind and who its customers are.
If the terms ‘Substantial Completion’ and ‘Beneficial Occupancy’ are cited in your Contract terms, they should also be defined in the Contract – as we have seen in other threads, the same terms used in different Contracts (and in different parts of the world) may have different meanings. Moreover, it is unlikely that you will unearth a ‘legal’ definition of these terms as they will (or should) be defined within the Contract, and not at law.
That said (GULP!!), ‘Substantial Completion’ is usually synonymous with ‘Practical Completion’, i.e., it represents the point at which the Contractor usually essentially completes the Works and it represents the start of the Contract’s Maintenance (or Guarantee) Period. Things such as the Contractor’s Construction All-Risk Insurance normally end at this point, and it usually is the date by which the end of the construction period is required.
Therefore, LADs etc will often be calculated from the Substantial Completion date if applicable.
‘Beneficial Occupancy’ is often used to represent the situation where the Employer can gain early access to, and occupy, his project prior to Substantial Completion, and in itself it may be a cause of delay and disruption to the completion of the Works by the Contractor.
As to the point from which LADs are calculated, this should be clear from your Contract (or it is really badly drafted!!), but I would hazard a guess that they are more likely to be calculated from ‘Substantial Completion’ than from any other milestone in your schedule.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Everyone, thank you for your advice and tips.
Regards,
Paul
Stuart,
Youre probably right or there doesnt seem much point in defining the two seperately. It may be a case of partial occupancy is required by the Employer and so it is being used as a form of sectional completion.
As we dont know all the facts, one guess is as good as another!
Andrew is right when he notes that the correct answer is dependant upon the specific wording of the Contract, which is the opening point in my answer below! ;-)
In my experience ‘Beneficial Occupancy’ takes place ahead of Substantial Completion. Substantial Completion is the point at which the Works are considered to be complete and from which LADs would commence, AND at which point the Employer would normally occupy the Works.
If the Employer occupies the Works at the point of Substantial Completion, (which is the normal case) it is difficult to see where the added benefit is. On this basis, I would suggest that Substantial Completion and Beneficial Occupancy cannot be the one and the same thing.
Cheers,
Stuart
www.rosmartin.com
Somewhere between Ronalds and Stuarts answer is the correct answer depending on the contract wording. Both are correct in what they say.
It may be the case that if the ocupancy is of the whole of the works and not just a section then the date of substantial completion and date of beneficial occupancy may be one and the same.
Substantial completion is often (but not always - read the contract) defined as the point at which the Employer starts or could have started to gain benefit from the object being built.
“Substantial Completion” often refers to the point in a project where the Owner is able to use the facility for its intended purpose. This means different things depending upon what type of facility you have in mind and who its customers are.
Hi Paul,
If the terms ‘Substantial Completion’ and ‘Beneficial Occupancy’ are cited in your Contract terms, they should also be defined in the Contract – as we have seen in other threads, the same terms used in different Contracts (and in different parts of the world) may have different meanings. Moreover, it is unlikely that you will unearth a ‘legal’ definition of these terms as they will (or should) be defined within the Contract, and not at law.
That said (GULP!!), ‘Substantial Completion’ is usually synonymous with ‘Practical Completion’, i.e., it represents the point at which the Contractor usually essentially completes the Works and it represents the start of the Contract’s Maintenance (or Guarantee) Period. Things such as the Contractor’s Construction All-Risk Insurance normally end at this point, and it usually is the date by which the end of the construction period is required.
Therefore, LADs etc will often be calculated from the Substantial Completion date if applicable.
‘Beneficial Occupancy’ is often used to represent the situation where the Employer can gain early access to, and occupy, his project prior to Substantial Completion, and in itself it may be a cause of delay and disruption to the completion of the Works by the Contractor.
As to the point from which LADs are calculated, this should be clear from your Contract (or it is really badly drafted!!), but I would hazard a guess that they are more likely to be calculated from ‘Substantial Completion’ than from any other milestone in your schedule.
Hope this helps,
Stuart
www.rosmartin.com