1. I have re-worded your example ( see below ) to test my understanding. Does what I have written make sense. I dont see how we go from 4 to 8 man days in (b) below ?
2. Does the "Freeze resource units per time period" check box get checked / unchecked only at the beginning of a project or can this happen at the statusing stage ? Are you indicating that this can happen at the statusing stage above after 8 days into this 10 day activity ?
3. Does checking the box in any way break the given formula ? ( I have the Harris book on P3 but not the software ( at this stage ) so have no way of setting up a test schedule ).
4. Is there a good no nonsense book that explains planning / cost theory implemented in P3 ?
Thanks again
Jim
"Freeze resource units per time period" applies to the following formula:
In this formula you can select which variable is constant. Then you only need to update one variable and the system will calculate the second variable based on the constant and the input - rather than updating two variables each time an activity is progressed.
If "(number of resource units/time period)" becomes frozen then this variable becomes constant.
Heres an example to explain "Freeze resource units per time period":
You have an activity which is 10 days in duration.
If you need a resource of 2 engineers per day for the whole period of this activity then you will need 20 engineer man days.
8 days into the activity ( 16 actual man days of resource have been used ) the job still requires 4
man days of work.
(a) If the number of resource units per time period is NOT frozen ( i.e., the box is not checked on the AutoCost form ) then the system will calculate that there are 4 remaining engineer man days and allocate these ( just as already budgeted ), i.e., an allocation of 2 engineers per day for the RD.
(b) If the number of resource units per time period is frozen ( i.e., the box is checked on the AutoCost form ) then during the remaining duration you will still have 2 engineers per day and your remaining budget is 8 engineer man days instead of 4.
you have a activity which is 10 day duration if you need 2 engineer per days for the whole period then you will need 20 engineer man days
After 8 day the activity started. you estimated it will still require remaining 4 days of works. And the actual man day used is 16 engineer man days.
If the resource unit per time period is "NOT" freezed
then because your remaining budgeted engineer man days is 4 (20-16) therefore the remaining 4 days the system will calculated and give the activity 1 engineer per days.
If the resource unit per time period is freezed then during your remaining duration you will still have 2 engineer per day that means you remaining budget is 8 engineer man days instead of 4.
In this fomular you can select which variable is a constant
then you will only need to update one variable then the system will calculate the second variable base on the constant and the input. Rather than update all three variable each time to progress an activity.
I found that when I was learning P3 (rather Finest Hour as it was then) it was helpful to try these options on a small (5 to 10 activity) test schedule. Print out reports from the default settings first then make changes to incorporate the various options, progress the schedule and again print the results for comparison. Its a bit time consuming, but you do learn whats what.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Alex,
I now see what you mean: I understand.
Ignore my previous post its rubbish.
Many Thanks,
Jim.
Hi Alex,
I dont see how we get 8 engineer man days.
Regards,
Jim
Thanks Alex. I have a few questions:
1. I have re-worded your example ( see below ) to test my understanding. Does what I have written make sense. I dont see how we go from 4 to 8 man days in (b) below ?
2. Does the "Freeze resource units per time period" check box get checked / unchecked only at the beginning of a project or can this happen at the statusing stage ? Are you indicating that this can happen at the statusing stage above after 8 days into this 10 day activity ?
3. Does checking the box in any way break the given formula ? ( I have the Harris book on P3 but not the software ( at this stage ) so have no way of setting up a test schedule ).
4. Is there a good no nonsense book that explains planning / cost theory implemented in P3 ?
Thanks again
Jim
"Freeze resource units per time period" applies to the following formula:
Remaining Budget = Remaining duration * (number of resource units/time period)
NF: 4 ( calculated )= 2 ( variable ) * 2 ( variable )
F : 8 ( ?? ) = 2 ( variable ) * 4 ( ?? )
In this formula you can select which variable is constant. Then you only need to update one variable and the system will calculate the second variable based on the constant and the input - rather than updating two variables each time an activity is progressed.
If "(number of resource units/time period)" becomes frozen then this variable becomes constant.
Heres an example to explain "Freeze resource units per time period":
You have an activity which is 10 days in duration.
If you need a resource of 2 engineers per day for the whole period of this activity then you will need 20 engineer man days.
8 days into the activity ( 16 actual man days of resource have been used ) the job still requires 4
man days of work.
(a) If the number of resource units per time period is NOT frozen ( i.e., the box is not checked on the AutoCost form ) then the system will calculate that there are 4 remaining engineer man days and allocate these ( just as already budgeted ), i.e., an allocation of 2 engineers per day for the RD.
(b) If the number of resource units per time period is frozen ( i.e., the box is checked on the AutoCost form ) then during the remaining duration you will still have 2 engineers per day and your remaining budget is 8 engineer man days instead of 4.
Jim,
Freeze resource unit per time period -
example
you have a activity which is 10 day duration if you need 2 engineer per days for the whole period then you will need 20 engineer man days
After 8 day the activity started. you estimated it will still require remaining 4 days of works. And the actual man day used is 16 engineer man days.
If the resource unit per time period is "NOT" freezed
then because your remaining budgeted engineer man days is 4 (20-16) therefore the remaining 4 days the system will calculated and give the activity 1 engineer per days.
If the resource unit per time period is freezed then during your remaining duration you will still have 2 engineer per day that means you remaining budget is 8 engineer man days instead of 4.
the fomular is like this
Remaining Budget = Remaining duration * (resource unit/time period)
In this fomular you can select which variable is a constant
then you will only need to update one variable then the system will calculate the second variable base on the constant and the input. Rather than update all three variable each time to progress an activity.
HTH
Alex
Jim,
I found that when I was learning P3 (rather Finest Hour as it was then) it was helpful to try these options on a small (5 to 10 activity) test schedule. Print out reports from the default settings first then make changes to incorporate the various options, progress the schedule and again print the results for comparison. Its a bit time consuming, but you do learn whats what.
Good Luck
Paul Silver