Reference post #11. I think your suggestion works with the caveat that non-filtered resources may appear as overallocations, but if you see 'green' bars then you have your filtered resources, or so it appears.
In my case (P6 8.2), I wanted to see the Resource Usage for only the filtered activities (WBS code, but it could have been anything) to manually level. Before using your hint, I would see resource usage for the entire project, not just the filtered activities.
It works best for me when only looking at "Budgeted" hours. Using "Early" hours provided extraneous data.
What i wanted to do was to produce a resource profile for only the filtered activties.
I first filterd out the activties and then in the Display option of profile i unchecked the Show All Projectsand this was what that solved my problem.
With release 5.0 you will also be able to see the over-allocated part of the resource profile, as part of the filtered profile, even when the load is below the threshold as a result of that filter; you should see it, because its really neat!
There is no reason why the resource allocation profile should not work in combination with filters. In fact, the intersection between activities and resources (i.e. assignments) should be sliced from both angles and not just resources.
It does work properly if you deselect "Show Overallocation" and stick to "Remaining Early". It should however also work with over-allocations and Primavera is currently investigating that problem.
You will not get histograms in the Resource Usage Profile based on filtered activities because this profile does not do that. Some alternatives are using Activity Usage Profile, Resource Assignment view (and copying usage spreadsheet data to Excel for graphing) or you could write a report and output to a text file then import this into Excel for graphing.
However, if you do manage to find a way to get what you are after I think a lot of people would be interested.
Ill be happy to take a look Rashid but I would also recommend you to call the Primavera help desk. They may have a simple solution for what we are both overlooking.
I am in the process of leveling the project manually. In P3, my rotuine for such task was to first filter say excavation activties and then by seeing peaks in histogram i did adjustment to start dates.
I have tried all the options of ’open projects’, closed project etc but still not getting the histogram for the filtered activties.
Neik i’ll be sending you a private message to get your email address and would mail you an xer as i am unable to solve the issue. I would really appreiciate if you could sequeeze sometime to solve this problem.
It took me a while to figure this one out, and I hope I’ll be able to explain the problem.
If you go to the Resource Usage Profile, it will show "Open Projects Only". This is the "Resource Analysis" setting under "User Preferences" and not necessarily meaning that you have selected to view the open projects only. (Yes, I agree, this is very confusing.)
If you click on "Open Projects Only" it will probably show that "Show All Projects" is still active. Deselect this option and you will get what you want.
Instead of viewing the Resource Usage Profile, can you see what you want using the Activity Usage Profile? This will show a histogram (or curves) based on the filtered activities regardless of the resources used.
I have the option "open projects" marked and i ran a filter which brings out no activity. Even in this case when Gantt chart have not even a single activtiy, the resource histogram is showing the remaining quantites of resources.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Niek;
Reference post #11. I think your suggestion works with the caveat that non-filtered resources may appear as overallocations, but if you see 'green' bars then you have your filtered resources, or so it appears.
In my case (P6 8.2), I wanted to see the Resource Usage for only the filtered activities (WBS code, but it could have been anything) to manually level. Before using your hint, I would see resource usage for the entire project, not just the filtered activities.
It works best for me when only looking at "Budgeted" hours. Using "Early" hours provided extraneous data.
It seems to be working, thanks.
Thanks Rashid,
Problem solved.
Regards,
James,
What i wanted to do was to produce a resource profile for only the filtered activties.
I first filterd out the activties and then in the Display option of profile i unchecked the Show All Projectsand this was what that solved my problem.
Regards
Rashid
Rashid,
Can you please explain how you solved this problem.
I have spoken to the primavera help desk and they informed me that this couldnt be done.
Regards.
Good to hear Rashid!
With release 5.0 you will also be able to see the over-allocated part of the resource profile, as part of the filtered profile, even when the load is below the threshold as a result of that filter; you should see it, because its really neat!
Cheers,
Niek.
Thanks for the help as now i am able to get the profile for the filtered activties.
Regards
Rashid Iqbal
There is no reason why the resource allocation profile should not work in combination with filters. In fact, the intersection between activities and resources (i.e. assignments) should be sliced from both angles and not just resources.
It does work properly if you deselect "Show Overallocation" and stick to "Remaining Early". It should however also work with over-allocations and Primavera is currently investigating that problem.
Ill keep you posted.
Niek.
Rashid
You will not get histograms in the Resource Usage Profile based on filtered activities because this profile does not do that. Some alternatives are using Activity Usage Profile, Resource Assignment view (and copying usage spreadsheet data to Excel for graphing) or you could write a report and output to a text file then import this into Excel for graphing.
However, if you do manage to find a way to get what you are after I think a lot of people would be interested.
Regards
KB
Thanks, i would certainly do that.
Regards
Rashid
Ill be happy to take a look Rashid but I would also recommend you to call the Primavera help desk. They may have a simple solution for what we are both overlooking.
Cheers,
Niek.
Thanks again
I am in the process of leveling the project manually. In P3, my rotuine for such task was to first filter say excavation activties and then by seeing peaks in histogram i did adjustment to start dates.
I have tried all the options of ’open projects’, closed project etc but still not getting the histogram for the filtered activties.
Neik i’ll be sending you a private message to get your email address and would mail you an xer as i am unable to solve the issue. I would really appreiciate if you could sequeeze sometime to solve this problem.
Regards
Rashid
Rashid,
It took me a while to figure this one out, and I hope I’ll be able to explain the problem.
If you go to the Resource Usage Profile, it will show "Open Projects Only". This is the "Resource Analysis" setting under "User Preferences" and not necessarily meaning that you have selected to view the open projects only. (Yes, I agree, this is very confusing.)
If you click on "Open Projects Only" it will probably show that "Show All Projects" is still active. Deselect this option and you will get what you want.
Regards,
Niek.
Instead of viewing the Resource Usage Profile, can you see what you want using the Activity Usage Profile? This will show a histogram (or curves) based on the filtered activities regardless of the resources used.
Regards
KB
Neik,
Thanks for getting back.
I have the option "open projects" marked and i ran a filter which brings out no activity. Even in this case when Gantt chart have not even a single activtiy, the resource histogram is showing the remaining quantites of resources.
Please advise.
Regards
Rashid
Rashid,
The thing you want to take a look at is "stacked histogram" because that will allow to group resources and display them in one histogram.
If you want see histograms of the filtered activities only you should select "open projects only".
Hope this helps,
Niek.