P3 schedule from mandays to manhours
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hi,
The project Im on we dont have money uploaded and to be able to show both mandays and manhours I assign a cost of 10 for each manday. Earned Value can be calculated for both, you just specify whether its resource or cost based.
Hope this helps.
Alex
Jeffrey,
If you want to change from mandays to manhours:
a) check what is the allocated working hours per day.
b) make a copy of the current file and change the planning unit to hour.
c) then do all the necessary changes using global change.
If you just change the duration to manhours than I dont think there is any significant effect because you are merely converting the duration from 1 day to 24 hours, which is generally the same. That means your EV is still the same as before.
Regards.
Hi Steve,
Nothing will effect EV, We just mutiply Mandays to Manhours in GlobalChange and generate in report writer but if we change the origin Data from Mandays to Manhours of cause it will totaly change the EV. It will create more works to be done.
What effect do you think this will have on the way Earned Value is calculated ?
Hi Jeff,
You can try to copy the project (Tools, Project Utilities, Copy) and then change the planning units there. You can then make the changes using Global Change
Hi Jeff,
I suggest u use global change.