The spreadsheet field option gives a choice among "Remaining Units", "Actual Units" and "Budgeted Units" only. it does not give option of baseline unit. Can you explain me how to add baseline units as an additional option?
You cant do it with the WYSIWYG. Try Resource/Cost Graphics. Go to Tools, Graphics Reports, Resource and Cost. In the content section you can select from Current schedule, Target 1 or Target 2.
My apologies. Being only a humble user of P3 Ver 3.1 I forgot I was in a P3e thread. Actually I have my upgrade to P3e but due to current project pressures have not loaded it yet. I guess you will be getting queries from me once I start delving into its workings in the near future.
The profile thus generaged are always from the current programme. I want to generate a profile which shows both baseline and current information. Is there a way to do it?
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Bijaya,
Take a look at the Activity Usage Profile (View / Show on Bottom Menu) . This will allow you to display current vs baseline.
Regards,
Bill
Paul,
It may be different version of programme (I am using P3e/c ver 4.1) but I dont see "Graphical Report" in pull down menu.
Steve,
The spreadsheet field option gives a choice among "Remaining Units", "Actual Units" and "Budgeted Units" only. it does not give option of baseline unit. Can you explain me how to add baseline units as an additional option?
In the Resource View, select the spreadsheet filds option and from the list of available fields choose Baseline Units.
Bijaya,
You cant do it with the WYSIWYG. Try Resource/Cost Graphics. Go to Tools, Graphics Reports, Resource and Cost. In the content section you can select from Current schedule, Target 1 or Target 2.
Good Luck
Paul Silver
Simple
Firstly you select Resource Usage Profile in the activities View
Secondly you format Resource Usage Profile Option (Right Click in the Graph Area)
Select unit, Tick on Budgeted By Date
Go to the Grahp TAB and tick Calculate Average
And change the divided total by to (0.01) and change the unit of Measure to (%)
Change Time scale to Day month or Week
That way you will resolve the problem not able to display the exact % of time each of your resource.
The reason that your original graph have 1 1 is because the rounding problem by effectively convert the usage to % it become more clear in the Usage %
HTH
Alex
P.S.
I can display a sample if you r interest PM me with your e-mail
Bijaya,
My apologies. Being only a humble user of P3 Ver 3.1 I forgot I was in a P3e thread. Actually I have my upgrade to P3e but due to current project pressures have not loaded it yet. I guess you will be getting queries from me once I start delving into its workings in the near future.
Paul
This is a further question on this topic.
The profile thus generaged are always from the current programme. I want to generate a profile which shows both baseline and current information. Is there a way to do it?