% completion link/unlink RD and Actuals

B
Bill McMichael 👤 Member for 21 years 6 months

To recalculate actual units and costs when % compl changes, there is a project level option to set this. Go to the project’s screen, select your project, and choose calculations tab on the bottom form.



There is also a % compl type setting for each activity. For activities where you want the percent complete to be independent of durations, units, and costs, choose "physical". This can be set either in columns or on the activity form -- general tab. When you show Activity % as a column, it will display the appropriate percent complete.



Regards,

Bill

R
Rashid Iqbal 👤 Member for 21 years 1 month

Thanks for answering though i am trying to figure out the same in P3e/c.



Regards

Rashid Iqbal

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts