% completion link/unlink RD and Actuals
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Thanks Bill, Ill try your suggestions.
Regards
Rashid
To recalculate actual units and costs when % compl changes, there is a project level option to set this. Go to the projects screen, select your project, and choose calculations tab on the bottom form.
There is also a % compl type setting for each activity. For activities where you want the percent complete to be independent of durations, units, and costs, choose "physical". This can be set either in columns or on the activity form -- general tab. When you show Activity % as a column, it will display the appropriate percent complete.
Regards,
Bill
Thanks for answering though i am trying to figure out the same in P3e/c.
Regards
Rashid Iqbal
Hi ,
U just go to tools > option > autocost rules and unlink RD.
regards