Beg to differ, but hammocks and group summaries show the elapsed duration i.e from the earliest early start date until the latest early finish date, not the sum of the durations.
Try using the $tmp functionality in Global change, or use Excel.
u can go to > format >organize >and there is a form "Group By" , so u can see total, click on that box, there is option top or bottom, then organize ....u can see the result.
but i dont understand your question, what to do with global change...? can u explain on that so i can help....
I tried it (CDI) but not worked because the variable assumes the value of OD on each Activity and not the sum of all OD. Did you understand ? I need the sum of all OD and store this sum in a variable that i can use in a global change.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
hi
creat a dummy resource for ex.(durn)
by global change let it equal to od then organize by resource or deal it as u want
Hi,

Attach is the sample for your review.
Regards.
Nilo,
First
Go to: Custom Data Items > Activity tab and create Sum Orig Dur (SODR) and type as N (Numeric).
Second
Go to: Global Change > Change tab > Then: SODR=EQ=OD and Run.
You will get the duration for each individual activity and the total duration for each coding.
HTH.
Thanks all !!!
But i don´t want use Excel. I wanna do it into the primavera.
Thought Nilo is asking for the subtotal/total figures as appearing on summary bars. Anyway, what is your feedback Nilo?
Steven, I couldnt find &tmp in P3 help. What is the full name of the function?
Regards.
Hi Suku,
Go to - Help - Global change- Temporary variables.
It is explained better with 2 examples .
HTH.
Sorry, I remember now its &tmp. Look in the help
Hi,
Excel would be the best way of doing it.
Steven could u tell me more about $temp functionality.
Thanx.
Beg to differ, but hammocks and group summaries show the elapsed duration i.e from the earliest early start date until the latest early finish date, not the sum of the durations.
Try using the $tmp functionality in Global change, or use Excel.
HTH
Hi,
Use Hammock activity. The function is same like subtotal bar. It will give the sum of OD for each grouping. Then you can store it as CDI.
Regards.
dear Mr nilo
u can go to > format >organize >and there is a form "Group By" , so u can see total, click on that box, there is option top or bottom, then organize ....u can see the result.
but i dont understand your question, what to do with global change...? can u explain on that so i can help....
cheers
Are you sure u dont want to try this outside P3 ? Trying to Subtotal the grouping by activity codes in Excel could be one alternative.
Also try looking at Resources if CDI dont serve your purpose.
I tried it (CDI) but not worked because the variable assumes the value of OD on each Activity and not the sum of all OD. Did you understand ? I need the sum of all OD and store this sum in a variable that i can use in a global change.
Thanks !!
Perhaps you could try to store it as a Custom data item or as a Resource.
Mary