After you combine the different projects into 1 master project, open the master project and for each external sub-project, add a constraint for each of the sub-project constraining the Start and Finish date. What this does is lock the start and finish date for this external sub-project.
Afte this you can time analyze.
The beauty of this, is that you can assign access rights to the external sub-project so that others can manage these sub-projects, while at your level you can see all of the rollups at master level.
Member for
20 years 9 monthsRE: Setting up multiproject in OPE
Hi Rodek,
After you combine the different projects into 1 master project, open the master project and for each external sub-project, add a constraint for each of the sub-project constraining the Start and Finish date. What this does is lock the start and finish date for this external sub-project.
Afte this you can time analyze.
The beauty of this, is that you can assign access rights to the external sub-project so that others can manage these sub-projects, while at your level you can see all of the rollups at master level.
Regards,
Hermie