Dear Ronald as I understand you have 3 problems with P3e can be summarized as follow
1- you cant make copy of the project.
Answer: from menu click Enterprice then choose project,and you will find windwos contain all project
choose the project you want to copy and click by right mouse and click copy then Past
so the copy of the project is more easy in P3e
2- You think Importing project will override the existing project.
Answer:When you Import project you have many choices for the Importing project you can update the existing project or make a new project,
you can find this option when you import project in the project wizard you will find this window "Import Project Option" click Import action and choose Creat new project
3- You cant use the previous update as Baseline
Answer: If you copy the project and update it and export to client and the client importe it with option creat new project he can open the new update and assign the old update as baseline
try this and if you find any problem contact me in my email
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear Ronald as I understand you have 3 problems with P3e can be summarized as follow
1- you cant make copy of the project.
Answer: from menu click Enterprice then choose project,and you will find windwos contain all project
choose the project you want to copy and click by right mouse and click copy then Past
so the copy of the project is more easy in P3e
2- You think Importing project will override the existing project.
Answer:When you Import project you have many choices for the Importing project you can update the existing project or make a new project,
you can find this option when you import project in the project wizard you will find this window "Import Project Option" click Import action and choose Creat new project
3- You cant use the previous update as Baseline
Answer: If you copy the project and update it and export to client and the client importe it with option creat new project he can open the new update and assign the old update as baseline
try this and if you find any problem contact me in my email
[email protected]
Best Regards